Overview
M3M MANSION PH-2
UNION BUILDMART PRIVATE LIMITED · Gurugram
Units244
Completion2032-02-29Proposed
Registered on2025-02-20
Valid to2031-02-28
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 10 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 63 documents · 3 source links |
Registration
Registration
| Promoter | UNION BUILDMART PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/916/648/2025/19 DATED 20.02.2025 | |
| Registered on | 2025-02-20 | |
| Valid to | 2031-02-28 | |
| Status (as filed) | Registered | |
| Proposed completion | 2032-02-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | DTCP License no 229 of 2023 dated 02.11.2023 | Town & Country Planning Department | |
| Layout Plan | 2025-01-27 | ||
| Building Plan | 2025-01-27 | ||
| I. LICENSE APPROVAL | 2023-11-02 | ||
| II. LOI APPROVAL | 2023-04-18 | ||
| III. CONSTRUCTION WATER ASSURANCE | 2023-12-01 | ||
| IV. DRINKING WATER ASSURANCE | 2023-12-01 | ||
| V. STORM WATER CONNECTION ASSURANCE | 2023-11-07 | ||
| VI. SEWERAGE CONNECTION ASSURANCE | 2023-12-01 | ||
| VII. ENVIRONMENT CLEARANCE | 2024-05-19 | ||
| VIII. FOREST NOC | 2018-08-07 | ||
| IX. BUILDING PLAN APPROVAL (BRIII) | 2025-01-27 | ||
| X. ROAD ACCESS PERMISSION | 2024-05-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,68,85,91,000.0000005 | |
|---|---|---|
| Construction | ₹2,93,99,27,000 | |
| Total | ₹11,20,38,08,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 5.12 | |
|---|---|---|
| Units | 244 |
Unit types
| Apartment/Shops/Other Buildings | 138.89 | 60 |
| Apartment/Shops/Other Buildings | 141.21 | 30 |
| Apartment/Shops/Other Buildings | 141.68 | 30 |
| Apartment/Shops/Other Buildings | 158.33 | 4 |
| Apartment/Shops/Other Buildings | 181.59 | 3 |
| Apartment/Shops/Other Buildings | 187.85 | 60 |
| Apartment/Shops/Other Buildings | 189.06 | 53 |
| Apartment/Shops/Other Buildings | 284.68 | 1 |
| Apartment/Shops/Other Buildings | 287.53 | 1 |
| Apartment/Shops/Other Buildings | 386.94 | 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-02-01 | |
|---|---|---|
| Proposed completion | 2032-02-29 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | UNION BUILDMART PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LIMITED | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/3280
- https://nominatim.openstreetmap.org/search?q=sector+113%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2025-02-20
- SEWRAGW CONNECTION ASSURANCE · 2025-01-24 · Sign in to download
- T-A ELEVATION-2 · 2025-02-18 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2025-01-24 · Sign in to download
- ARAVALI NOC · 2025-01-24
- STRUCTURAL PLAN-1 · 2025-02-18
- JAMABANDI · 2025-02-18 · Sign in to download
- STRUCTURAL PLAN-4 · 2025-02-18
- STRUCTURAL PLAN-6 · 2025-02-18
- T-B ELEVATION PLAN-2 · 2025-02-18
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2025-01-24
- T-B SECOND FLOOR LAYOUT · 2025-02-18 · Sign in to download
- ENVIRONMENT CLEARANCE · 2025-02-18
- LOI · 2025-02-18 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2025-01-24
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2025-01-24
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2025-01-24 · Sign in to download
- LOI · 2025-01-24 · Sign in to download
- LC VI · 2025-01-24 · Sign in to download
- JAMABANDI · 2025-01-24 · Sign in to download
- INFORMATION TO REVENUE DEPARTMENT · 2025-01-24 · Sign in to download
- EC · 2025-01-24 · Sign in to download
- TSR · 2025-01-24 · Sign in to download
- FOREST NOC · 2025-01-24
- CONSTRUCTION WATER ASSURANCE · 2025-01-24 · Sign in to download
- DRINKING WATER ASSURANCE · 2025-01-24 · Sign in to download
- STORM WATER CONNECTION ASSURANCE · 2025-01-24 · Sign in to download
- T-B TERRACE & MUMTY PLAN · 2025-02-18
- SITE PLAN WITH SERVICES · 2025-02-18
- REP-II · 2025-02-18 · Sign in to download
- STRUCTURAL PLAN-5 · 2025-02-18
- T-B FIRST FLOOR LAYOUT · 2025-02-18 · Sign in to download
- T-B ELEVATION PLAN-1 · 2025-02-18
- STRUCTURAL PLAN-3 · 2025-02-18
- T-A STILT LEVEL LAYOUT · 2025-02-18 · Sign in to download
- STRUCTURAL PLAN-2 · 2025-02-18
- T-A 27TH,28TH &30TH; FLOOR LAYOUT · 2025-02-18 · Sign in to download
- T-A SECOND FLOOR LAYOUT · 2025-02-18 · Sign in to download
- T-B TYPICAL(19TH,29TH) FLOOR LAYOUT · 2025-02-18 · Sign in to download
- FIRE SCHEME APPLICATION · 2025-02-18 · Sign in to download
- MUTATION · 2025-02-18 · Sign in to download
- T-B SECTION YY · 2025-02-18 · Sign in to download
- LICENSE · 2025-02-18
- T-A SECTION-XX · 2025-02-18 · Sign in to download
- T-A SECTION-YY · 2025-02-18 · Sign in to download
- T-A PENTHOUSE FLOOR LVL LAYOUT · 2025-02-18 · Sign in to download
- T-A TYPICAL 3RD TO 18TH, 20TH TO 26TH FLOOR PLAN · 2025-02-18
- RAPAT · 2025-02-18 · Sign in to download
- T-A FIRST FLOOR LAYOUT · 2025-02-18 · Sign in to download
- SERVICE PLANS & ESTIMATES APPLICATION · 2025-02-18
- T-B TYPICAL 3RD TO 18TH, 20TH TO 28TH & 30TH FLOOR LAYOUT · 2025-02-18 · Sign in to download
- T-A TERRACE & MUMTY FLOOR LAYOUT · 2025-02-18 · Sign in to download
- SIZRA · 2025-02-18 · Sign in to download
- BR-III · 2025-02-18 · Sign in to download
- DEMARCATION PLAN · 2025-02-18
- REVISED ZONING PLAN · 2025-02-18
- SITE PLAN · 2025-02-18
- T-A 19TH&29TH; FLOOR LAYOUT · 2025-02-18 · Sign in to download
- T-A ELEVATION-1 · 2025-02-18 · Sign in to download
- T-B PENTHOUSE FLOOR · 2025-02-18 · Sign in to download
- T-B SECTION-XX · 2025-02-18 · Sign in to download
- T-B STILT LEVEL LAYOUT · 2025-02-18 · Sign in to download
- Amendment in the Registration Certificate- Change of name of the group housing project from "M3M Mansion Ph-2" to "M3M St. Andrews at SCDA". · 2025-06-05 · Sign in to download