Overview
M3M URBANA
M3M INDIA PVT. LTD. & MARTIAL BUILDCOM PVT. LTD. · Gurugram
Completion2021-12-31Revised
Registered on2019-06-18
Valid to2021-12-31
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 7 unit types |
| Construction & progress | 1 progress detail |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 16 documents · 3 source links |
Registration
Registration
| Promoter | M3M INDIA PVT. LTD. & MARTIAL BUILDCOM PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/341/73/2019/35 DATED 18.06.2019 | |
| Registered on | 2019-06-18 | |
| Valid to | 2021-12-31 | |
| Status (as filed) | Registered | |
| Revised completion | 2021-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 11 of 2011 dated 28.01.2011 | Town & Country Planning Department | |
| Layout Plan | 2016-04-04 | ||
| Building Plan | 2017-11-30 | ||
| I. FOREST NOC | 2011-12-30 | ||
| II. AIRPORT HEIGHT CLEARANCE NOC | 2016-04-18 | ||
| III. HUDA CONSTRUCTION WATER NOC | 2012-09-12 | ||
| IV. ELECTRICAL LOAD AVAILABILITY | 2016-08-22 | ||
| V. ENVIRONMENTAL CLEARANCE | 2013-07-12 | ||
| VI. CONSENT TO ESTABLISH | 2016-05-06 | ||
| VII. FIRE SCHEME APPROVAL | 2014-04-09 | ||
| VIII. SERVICES ESTIMATES | 2015-11-23 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹16,58,00,000 | |
|---|---|---|
| Construction | ₹1,18,38,00,000 | |
| Total | ₹2,10,71,29,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 28,721.56 |
|---|
Unit types
| 1 | 279 |
| 2 | 52 |
| 3 | |
| 4 | 37 |
| 5 | 53 |
| 6 | 50 |
| 7 | 100 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Revised completion | 2021-12-31 |
|---|
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M3M INDIA PVT. LTD. & MARTIAL BUILDCOM PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/411
- https://nominatim.openstreetmap.org/search?q=sector+67%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2019-06-18
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-02-16
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-02-20 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-02-18
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2019-02-04 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-02-04
- ENVIRONMENT CLEARANCE · 2019-02-04
- ZONING PLAN · 2019-02-04
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-02-04
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-02-27
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-02-27 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-02-20 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-06-13 · Sign in to download
- Occupation Certificate · 2023-07-28 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download