Overview
MAA DURGA APARTMENT
R K HOME · Patna
Booked0As of 2026-06-30
Construction progress20%As of 2026-06-30
Completion2027-03-20Proposed
Registered on2024-04-04
Valid to2027-03-20
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details |
| Construction & progress | 4 progress details · 5 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 9 source links |
Registration
Registration
| Promoter | R K HOME | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP73418-002/133/R-1662/2024 | |
| Registered on | 2024-04-04 | |
| Valid to | 2027-03-20 | |
| Project type | Residential | |
| Status (as filed) | RERA Registered Projects | |
| Proposed completion | 2027-03-20 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Valid to | Authority |
|---|---|---|
| Environment Clearance | 0 | |
| Fire NOC | 2033-12-10 | Fire Dept Bihar |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,00,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,301.31 | |
|---|---|---|
| Built-up (m²) | 8,094 | |
| FAR | 2.45 | |
| Towers | 2 | |
| Booked | 0 | |
| Booked as of | 2026-06-30 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 20% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2023-03-20 | |
| Proposed completion | 2027-03-20 |
Quarterly progress
| 2026-Q2 | 2026-09-04 | 20% | 0 |
| 2026-Q1 | 2026-04-30 | ||
| 2025-Q4 | 2026-01-31 | ||
| 2025-Q3 | 2025-10-31 | ||
| 2025-Q2 | 2025-08-20 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | R K HOME | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | INDIAN BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP04042023173418_002
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP04042023173418&ld=pan&pj=RERAP04042023173418_002&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP04042023173418_002
- https://rera.bihar.gov.in/RCpage.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Sanctioned Building Plan
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- CA certificate · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Sanction Certificate for Bank Construction Finance · Sign in to download
- Upload Sanctioned Layout Plan
- Other (if any) · Sign in to download
- Q1 (Apr - Jun) / 2026-2027 · 2026-09-04
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-30
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-31
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-31
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-20
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2026-Q1 · 2026-04-30
- 2025-Q4 · 2026-01-31
- 2025-Q3 · 2025-10-31
- 2025-Q2 · 2025-08-20