Overview
MAA SHANTI PAILESH
DURGA HOME CONSTRUCTION · Patna
Units24
Completion2022-12-31Proposed
Registered on2019-11-26
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 7 unit types |
| Construction & progress | 2 progress details · 13 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 18 source links |
Registration
Registration
| Promoter | DURGA HOME CONSTRUCTION | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP65704-1/1011/R-850/2019 | |
| Registered on | 2019-11-26 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,079.48 | |
|---|---|---|
| Built-up (m²) | 2,131.22 | |
| FAR | 1.99 | |
| Towers | 1 | |
| Units | 24 |
Unit types
| 2 BHK | 3 | MAA SHANTI PAILESH |
| 2 BHK | 3 | MAA SHANTI PAILESH |
| 2 BHK | 3 | MAA SHANTI PAILESH |
| 2 BHK | 3 | MAA SHANTI PAILESH |
| 3 BHK | 3 | MAA SHANTI PAILESH |
| 3 BHK | 3 | MAA SHANTI PAILESH |
| 3 BHK | 6 | MAA SHANTI PAILESH |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-06-17 | |
|---|---|---|
| Proposed completion | 2022-12-31 |
Quarterly progress
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2024-07-25 |
| 2022-Q4 | 2023-02-18 |
| 2022-Q3 | 2023-03-23 |
| 2022-Q2 | 2022-10-18 |
| 2022-Q1 | 2022-04-19 |
| 2021-Q4 | 2022-04-19 |
| 2021-Q3 | 2022-04-19 |
| 2021-Q2 | 2022-04-19 |
| 2021-Q1 | 2022-04-19 |
| 2020-Q4 | 2021-01-18 |
| 2020-Q3 | 2021-01-18 |
| 2020-Q2 | 2020-09-09 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DURGA HOME CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP06112019165704-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP06112019165704-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2023-02-18
- Q2-Jul to Sep / 2022-2023 · 2023-03-23
- Q1-Apr to Jun / 2022-2023 · 2022-10-18
- Q4-Jan to Mar / 2021-2022 · 2022-04-19
- Q3-Oct to Dec / 2021-2022 · 2022-04-19
- Q2-Jul to Sep / 2021-2022 · 2022-04-19
- Q1-Apr to Jun / 2021-2022 · 2022-04-19
- Q4-Jan to Mar / 2020-2021 · 2022-04-19
- Q3-Oct to Dec / 2020-2021 · 2021-01-18
- Q2-Jul to Sep / 2020-2021 · 2021-01-18
- Q1-Apr to Jun / 2020-2021 · 2020-09-09
- Notice of Commencement
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2023-02-18
- 2022-Q3 · 2023-03-23
- 2022-Q2 · 2022-10-18
- 2022-Q1 · 2022-04-19
- 2021-Q4 · 2022-04-19
- 2021-Q3 · 2022-04-19
- 2021-Q2 · 2022-04-19
- 2021-Q1 · 2022-04-19
- 2020-Q4 · 2021-01-18
- 2020-Q3 · 2021-01-18
- 2020-Q2 · 2020-09-09