Overview
Maa Vindhyavasni
SAI SAKSHI CONSTRUCTION PRIVATE LIMITED · Patna
Units28
Completion2021-03-31Proposed
Registered on2019-09-25
Approvals2
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 7 unit types |
| Construction & progress | 2 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 19 source links |
Registration
Registration
| Promoter | SAI SAKSHI CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP20134-1/1017/R-781/2019 | |
| Registered on | 2019-09-25 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2021-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum |
|---|---|
| RERA/C-CASE-372/2022 | RERA Bihar |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,10,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,132 | |
|---|---|---|
| Built-up (m²) | 2,746.93 | |
| FAR | 2.42 | |
| Towers | 1 | |
| Units | 28 |
Unit types
| 3 BHK | 4 | Maa Vindhyavasni |
| 2 BHK | 4 | Maa Vindhyavasni |
| 2 BHK | 4 | Maa Vindhyavasni |
| 3 BHK | 4 | Maa Vindhyavasni |
| 3 BHK | 4 | Maa Vindhyavasni |
| 3 BHK | 4 | Maa Vindhyavasni |
| 3 BHK | 4 | Maa Vindhyavasni |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-07-01 | |
|---|---|---|
| Proposed completion | 2021-03-31 |
Quarterly progress
| 2022-Q4 | 2023-02-11 |
| 2022-Q3 | 2022-11-21 |
| 2022-Q2 | 2022-07-14 |
| 2022-Q1 | 2022-04-20 |
| 2021-Q4 | 2022-01-17 |
| 2021-Q3 | 2021-10-22 |
| 2021-Q2 | 2021-10-22 |
| 2021-Q1 | 2021-10-22 |
| 2020-Q4 | 2021-10-22 |
| 2020-Q3 | 2021-10-22 |
| 2020-Q2 | 2021-10-22 |
| 2020-Q1 | 2021-10-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAI SAKSHI CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP05082019120134-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP05082019120134-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q3-Oct to Dec / 2022-2023 · 2023-02-11
- Q2-Jul to Sep / 2022-2023 · 2022-11-21
- Q1-Apr to Jun / 2022-2023 · 2022-07-14
- Q4-Jan to Mar / 2021-2022 · 2022-04-20
- Q3-Oct to Dec / 2021-2022 · 2022-01-17
- Q2-Jul to Sep / 2021-2022 · 2021-10-22
- Q1-Apr to Jun / 2021-2022 · 2021-10-22
- Q4-Jan to Mar / 2020-2021 · 2021-10-22
- Q3-Oct to Dec / 2020-2021 · 2021-10-22
- Q2-Jul to Sep / 2020-2021 · 2021-10-22
- Q1-Apr to Jun / 2020-2021 · 2021-10-22
- Q4-Jan to Mar / 2019-2020 · 2021-10-22
- Case proceeding RERA/C-CASE-372/2022 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- RERA/C-CASE-372/2022 · Sign in to download
- 2022-Q4 · 2023-02-11
- 2022-Q3 · 2022-11-21
- 2022-Q2 · 2022-07-14
- 2022-Q1 · 2022-04-20
- 2021-Q4 · 2022-01-17
- 2021-Q3 · 2021-10-22
- 2021-Q2 · 2021-10-22
- 2021-Q1 · 2021-10-22
- 2020-Q4 · 2021-10-22
- 2020-Q3 · 2021-10-22
- 2020-Q2 · 2021-10-22
- 2020-Q1 · 2021-10-22