Overview
MADHAV MARKET
Pee Cee Realty Builders Private Limited · Ansal Sushant City-1, Machwa Kalwar Road
Units129
Booked100 of 129As of 2026-09-30
Completion2025-11-30Revised · Proposed 2025-03-08
Registered on2025-05-15
Valid to2027-01-06
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 39 unit types |
| Construction & progress | 3 progress details · 1 quarter · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 8 source links |
Registration
Registration
| Promoter | Pee Cee Realty Builders Private Limited | |
|---|---|---|
| District | Jaipur | |
| Locality | Ansal Sushant City-1, Machwa Kalwar Road | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2025/3770 | |
| Registered on | 2025-05-15 | |
| Valid to | 2027-01-06 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2025-03-08 | |
| Revised completion | 2025-11-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,00,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹7,87,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q3 | ₹7,56,99,691 | ₹283.7 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,890.8 | |
|---|---|---|
| Built-up (m²) | 2,777.82 | |
| Towers | 129 | |
| Units | 129 | |
| Booked | 100 | |
| Booked as of | 2026-09-30 |
Unit types
| 96.53 Sq. Meters Plot No.- 1 | 1 | 1 |
| 23.24 Sq. Meters Plot No.- 2, 3, 4, 5, 6, 7, 8, 9, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 36, 37, 38, 39, 40, 41, 42, 43, 78, 79, 80, 81, 82, 83, 84, 85, 86, 89, 90, 91, 92, 93, 94, 95, 96, 97 | 54 | 52 |
| 36.73 Sq. Meters Plot No.- 10, 11, 34, 35 | 4 | 4 |
| 24.19 Sq. Meters Plot No.- 22 | 1 | 1 |
| 20.10 Sq. Meters Plot No.- 23 | 1 | 1 |
| 21.21 Sq. Meters Plot No.- 44 | 1 | 1 |
| 19.16 Sq. Meters Plot No.- 45 | 1 | 1 |
| 19.13 Sq. Meters Plot No.- 46 | 1 | 1 |
| 19.10 Sq. Meters Plot No.- 47 | 1 | 1 |
| 19.07 Sq. Meters Plot No.- 48 | 1 | 1 |
| 19.04 Sq. Meters Plot No.- 49 | 1 | 1 |
| 19.01 Sq. Meters Plot No.- 50 | 1 | 1 |
| 18.98 Sq. Meters Plot No.- 51 | 1 | 1 |
| 18.95 Sq. Meters Plot No.- 52 | 1 | 1 |
| 18.92 Sq. Meters Plot No.- 53 | 1 | 1 |
| 18.88 Sq. Meters Plot No.- 54 | 1 | 1 |
| 18.84 Sq. Meters Plot No.- 55 | 1 | 1 |
| 18.80 Sq. Meters Plot No.- 56 | 1 | 1 |
| 16.90 Sq. Meters Plot No.- 57 | 1 | 1 |
| 15.34 Sq. Meters Plot No.- 58, 59, 60, 61, 62, 63, 64, 65, 66 | 9 | 4 |
| 15.79 Sq. Meters Plot No.- 67 | 1 | 1 |
| 14.34 Sq. Meters Plot No.- 68 | 1 | 1 |
| 13.94 Sq. Meters Plot No.- 69, 70, 71, 72, 73, 74, 75, 76, 77 | 9 | 7 |
| 23.92 Sq. Meters Plot No.- 87, 88 | 2 | 2 |
| 18.61 Sq. Meters Plot No.- 98, 99, 100, 101, 102, 103, 104, 105, 106, 109, 110, 111, 112, 113, 114, 115, 116, 117 | 18 | 15 |
| 19.15 Sq. Meters Plot No.- 107 | 1 | 1 |
| 19.46 Sq. Meters Plot No.- 108 | 1 | 1 |
| 17.62 Sq. Meters Plot No.- 119 | 1 | 1 |
| 18.87 Sq. Meters Plot No.- 120 | 1 | 1 |
| 19.52 Sq. Meters Plot No.- 121 | 1 | 1 |
| 20.18 Sq. Meters Plot No.- 122 | 1 | 0 |
| 20.83 Sq. Meters Plot No.- 123 | 1 | 1 |
| 21.49 Sq. Meters Plot No.- 124 | 1 | 1 |
| 22.14 Sq. Meters Plot No.- 125 | 1 | 1 |
| 22.80 Sq. Meters Plot No.- 126 | 1 | 1 |
| 23.45 Sq. Meters Plot No.- 127 | 1 | 1 |
| 24.11 Sq. Meters Plot No.- 128 | 1 | 0 |
| 25.90 Sq. Meters Plot No.- 129 | 1 | 1 |
| 18.00 sq meters plot no. 118 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-03-08 | |
|---|---|---|
| Proposed completion | 2025-03-08 | |
| Revised completion | 2025-11-30 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2026-Q3 | 2026-09-03 | 100 |
Extensions
| Valid to |
|---|
| 2026-09-06 |
| 2027-01-06 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Pee Cee Realty Builders Private Limited | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AU SMALL FINANCE BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=jaipur%2C+Jaipur%2C+Rajasthan%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.rajasthan.gov.in/ProjectDetail?id=MiGzpQQBNqsQb8JrMQGbdg
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/MiGzpQQBNqsQb8JrMQGbdg
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=MiGzpQQBNqsQb8JrMQGbdg%3D%3D&QuarterIdEnc=%2BKD7QcnAdOtELCm57RAuQA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=WRDIY6ELo3w%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- FormFUploadedPathString · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Bankaffidavit · Sign in to download
- SitePlanPath · 2025-04-21
- SitePlanPath · 2025-04-21
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_filepath · Sign in to download
- R2_filepath · Sign in to download
- R3_filepath · Sign in to download
- RERABankStatementUpload · Sign in to download
- NoLienCertificateUpload
- Extension order · Sign in to download