Overview
MAGNUS PARK
MAGNUS HOUSING · Patiala
Units220
Completion2029-06-13Proposed
Valid to2029-06-13
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 12 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 34 documents · 22 source links |
Registration
Registration
| Promoter | MAGNUS HOUSING | |
|---|---|---|
| District | Patiala | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-PTL63-PR1058 | |
| Valid to | 2029-06-13 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-06-13 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| Electric Substation NOC | 2025-03-27 |
| License to develop colony or society from Competent Authority | |
| NOC from Mining Department | 2025-03-26 |
| NOC from NHAI/ PWD | 2024-05-08 |
| Other Document (FOREST NOC ) | 2024-05-21 |
| Other Document (Solid waste NOC) | 2024-08-08 |
| Pollution Clearance from Punjab Pollution Control Board | 2026-04-13 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-03-10 |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹15,94,99,702 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 38,595 | |
|---|---|---|
| Units | 220 |
Unit types
| 34 to 47 | 109.148 | 14 | RESIDENTIAL PLOTS |
| 48 to 55 | 104.5 | 8 | RESIDENTIAL PLOTS |
| 115 to 158 | 125.4 | 44 | RESIDENTIAL PLOTS |
| 159 to 181 | 117.508 | 23 | RESIDENTIAL PLOTS |
| 182 | 112.391 | 1 | RESIDENTIAL PLOTS |
| 01 to 07, 9 to 32, 56, 83 to 98 | 125.419 | 48 | RESIDENTIAL PLOTS |
| 08 and 33 | 120.751 | 2 | RESIDENTIAL PLOTS |
| 99 to 114 | 125.4 | 16 | INDEPENDENT FLOOR PLOTS |
| 57 to 62, 63 to 82 | 83.6 | 26 | EWS PLOTS |
| 07 to 19 | 52.015 | 13 | COMMERCIAL PLOTS OR SHOPS |
| 26 to 38 | 62.7 | 13 | COMMERCIAL PLOTS OR SHOPS |
| 01 to 06, 20 to 25 | 27.863 | 12 | COMMERCIAL PLOTS OR SHOPS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-06-13 | |
|---|---|---|
| Proposed completion | 2029-06-13 |
Quarterly progress
| 2024-Q4 | 2025-04-25 |
| 2025-Q1 | 2025-04-25 |
| 2024-Q3 | 2025-04-25 |
| 2025-Q2 | 2025-07-14 |
| 2025-Q3 | 2025-10-23 |
| 2025-Q4 | 2026-01-29 |
| 2026-Q1 | 2026-04-19 |
| 2026-Q2 | 2026-07-04 |
| 2026-Q3 | 2026-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAGNUS HOUSING | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Kotak Mahindra Bank Limited | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12058&inPromoter_ID=2954&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-03-27
- License to develop colony or society from Competent Authority
- NOC from Mining Department · 2025-03-26
- NOC from NHAI/ PWD · 2024-05-08
- Other Document (FOREST NOC ) · 2024-05-21
- Other Document (Solid waste NOC) · 2024-08-08
- Pollution Clearance from Punjab Pollution Control Board · 2026-04-13
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-10
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2025-03-27
- License to develop colony or society from Competent Authority
- NOC from Mining Department · 2025-03-26
- NOC from NHAI/ PWD · 2024-05-08
- Other Document (FOREST NOC ) · 2024-05-21
- Other Document (Solid waste NOC) · 2024-08-08
- Pollution Clearance from Punjab Pollution Control Board · 2026-04-13
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-10
- Consent details of actual owner of Land
- 2024-Q4 · 2025-04-25
- 2025-Q1 · 2025-04-25
- 2024-Q3 · 2025-04-25
- 2025-Q2 · 2025-07-14
- 2025-Q3 · 2025-10-23
- 2025-Q4 · 2026-01-29
- 2026-Q1 · 2026-04-19
- 2026-Q2 · 2026-07-04
- 2026-Q3 · 2026-10-12