DOSLKolkata, West Bengal Workspace

Overview

MAHABIRA

SHIVAM INFRAREALITY Pvt. Ltd. · Kolkata
Units42
Booked0 of 42As of 2024-09-30
Completion2024-09-30Revised · Proposed 2024-09-30
Registered on2020-01-10

Sections

Technical report
Site & area5 site details · 1 unit type
Construction & progress2 progress details · 1 quarter · 1 extension
Developer & finance
Developer2 developer details
The evidence
Sources24 documents · 9 source links

Registration

Registration

PromoterSHIVAM INFRAREALITY Pvt. Ltd.
DistrictKolkata
RegulatorWBHIRA
Registration numberHIRA/P/KOL/2020/000777
Registered on2020-01-10
Project typeResidential
Status (as filed)Under Construction
Proposed completion2024-09-30
Revised completion2024-09-30