Overview
MAHADEV INDUSTRIAL TOWNSHIP (MIT)
MAHADEV UNITED INFRASTRUCTURE PVT. LTD. · Sonipat
Units58
Completion2028-10-22Proposed
Valid to2028-10-22
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 22 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 9 documents · 3 source links |
Registration
Registration
| Promoter | MAHADEV UNITED INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| District | Sonipat | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-SNP-559-2024 | |
| Valid to | 2028-10-22 | |
| Status (as filed) | Registered | |
| Proposed completion | 2028-10-22 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | LICENSE NO. 218 OF 2023 DATED 23.10.2023 (VALID UPTO 22.10.2028) | Town & Country Planning Department | |
| Layout Plan | 2023-10-23 | ||
| Building Plan | |||
| I. LICENSE NO. 218 OF 2023 | 2023-10-23 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,95,63,750.00000001 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹17,27,20,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 58 |
|---|
Unit types
| Plot | 1 | |
| Plot | 7 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 3 | |
| Plot | 1 | |
| Plot | 6 | |
| Plot | 1 | |
| Plot | 6 | |
| Plot | 1 | |
| Plot | 5 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 16 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-12-15 | |
|---|---|---|
| Proposed completion | 2028-10-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAHADEV UNITED INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF BARODA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/print_quarterly_schedules/MQ==/MTM4NQ==/MjAyMw==
- https://haryanarera.gov.in/view_project/project_preview_open/2713
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2023-12-07
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2023-12-07
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2023-12-07
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2023-12-08 · Sign in to download
- corriegndum upload · 2024-09-18 · Sign in to download
- Suppplementary RC uploaded. · 2025-10-16 · Sign in to download
- Supplementary RC Uploaded · 2026-09-09 · Sign in to download
- Corrigendum Uploaded · 2026-09-22 · Sign in to download