DOSLJaipur, Rajasthan Workspace

Overview

MAHVEER ENCLAVE

BALAJI DEVELOPERS · Jaipur
Units53
Booked51 of 53As of 2025-12-31
Completion2026-01-31Revised · Proposed 2024-09-01
Registered on2024-09-02
Valid to2026-01-31

Sections

Property title & search report
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area6 site details · 26 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details
The evidence
Sources47 documents · 6 source links

Registration

Registration

PromoterBALAJI DEVELOPERS
DistrictJaipur
RegulatorRajasthan RERA
Registration numberRAJ/P/2024/3241
Registered on2024-09-02
Valid to2026-01-31
Project typePlotted
Status (as filed)COMPLETED
Proposed completion2024-09-01
Revised completion2026-01-31