Overview
Mandavi Prince Palace
Dr Jerry Vincent Dias · Udupi
Units173
Completion2029-09-30Revised · Proposed 2028-12-31
Registered on2018-01-20
Valid to2029-09-30
Approvals5
Complaints0
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals · 1 occupancy certificate |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 5 site details · 172 unit types |
| Construction & progress | 3 progress details · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 52 documents · 9 source links |
Registration
Registration
| Promoter | Dr Jerry Vincent Dias | |
|---|---|---|
| District | Udupi | |
| Regulator | K-RERA | |
| Registration number | PRM/KA/RERA/1273/318/PR/180120/001768 | |
| Registered on | 2018-01-20 | |
| Valid to | 2029-09-30 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | APPROVED | |
| Proposed completion | 2028-12-31 | |
| Revised completion | 2029-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approved Plan | Udupi Urban Development Authority |
| Commencement Certificate | |
| All NOCs from Authority | |
| NOC issued by the Fire Force department after completion of work | |
| Occupancy Certificate |
Occupancy certificate
| Status | Received | |
|---|---|---|
| Date | 2024-06-26 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹82,00,000 | |
|---|---|---|
| Construction | ₹45,00,00,000 | |
| Total | ₹45,82,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 11,457 | |
|---|---|---|
| FAR | 2.49 | |
| Towers | 2 | |
| Maximum floors | 14 | |
| Units | 173 |
Unit types
| 1BHK | 1 | Tower E | 1 |
| 2BHK | 1 | Tower E | 1 |
| 2BHK | 1 | Tower E | 1 |
| 2BHK | 1 | Tower E | 1 |
| 2BHK | 2 | Tower E | 1 |
| 1BHK | 1 | Tower E | 2 |
| 2BHK | 1 | Tower E | 2 |
| 2BHK | 1 | Tower E | 2 |
| 2BHK | 1 | Tower E | 2 |
| 2BHK | 1 | Tower E | 2 |
| 2BHK | 1 | Tower E | 2 |
| 1BHK | 1 | Tower E | 3 |
| 2BHK | 1 | Tower E | 3 |
| 2BHK | 1 | Tower E | 3 |
| 2BHK | 1 | Tower E | 3 |
| 2BHK | 1 | Tower E | 3 |
| 2BHK | 1 | Tower E | 3 |
| 1BHK | 1 | Tower E | 4 |
| 2BHK | 1 | Tower E | 4 |
| 2BHK | 1 | Tower E | 4 |
| 2BHK | 1 | Tower E | 4 |
| 2BHK | 1 | Tower E | 4 |
| 2BHK | 1 | Tower E | 4 |
| 1BHK | 1 | Tower E | 5 |
| 2BHK | 1 | Tower E | 5 |
| 2BHK | 1 | Tower E | 5 |
| 2BHK | 1 | Tower E | 5 |
| 2BHK | 1 | Tower E | 5 |
| 2BHK | 1 | Tower E | 5 |
| 1BHK | 1 | Tower E | 6 |
| 2BHK | 1 | Tower E | 6 |
| 2BHK | 1 | Tower E | 6 |
| 2BHK | 1 | Tower E | 6 |
| 2BHK | 1 | Tower E | 6 |
| 2BHK | 1 | Tower E | 6 |
| 1BHK | 1 | Tower E | 7 |
| 2BHK | 1 | Tower E | 7 |
| 2BHK | 1 | Tower E | 7 |
| 2BHK | 1 | Tower E | 7 |
| 2BHK | 1 | Tower E | 7 |
| 2BHK | 1 | Tower E | 7 |
| 1BHK | 1 | Tower E | 8 |
| 2BHK | 1 | Tower E | 8 |
| 2BHK | 1 | Tower E | 8 |
| 2BHK | 1 | Tower E | 8 |
| 2BHK | 1 | Tower E | 8 |
| 2BHK | 1 | Tower E | 8 |
| 1BHK | 1 | Tower E | 9 |
| 2BHK | 1 | Tower E | 9 |
| 2BHK | 1 | Tower E | 9 |
| 2BHK | 1 | Tower E | 9 |
| 2BHK | 1 | Tower E | 9 |
| 2BHK | 1 | Tower E | 9 |
| 1BHK | 1 | Tower E | 10 |
| 2BHK | 1 | Tower E | 10 |
| 2BHK | 1 | Tower E | 10 |
| 2BHK | 1 | Tower E | 10 |
| 2BHK | 1 | Tower E | 10 |
| 2BHK | 1 | Tower E | 10 |
| 1BHK | 1 | Tower E | 11 |
| 2BHK | 1 | Tower E | 11 |
| 2BHK | 1 | Tower E | 11 |
| 2BHK | 1 | Tower E | 11 |
| 2BHK | 1 | Tower E | 11 |
| 2BHK | 1 | Tower E | 11 |
| 1BHK | 1 | Tower E | 12 |
| 2BHK | 1 | Tower E | 12 |
| 2BHK | 1 | Tower E | 12 |
| 2BHK | 1 | Tower E | 12 |
| 2BHK | 1 | Tower E | 12 |
| 2BHK | 1 | Tower E | 12 |
| 1BHK | 1 | Tower E | 13 |
| 2BHK | 1 | Tower E | 13 |
| 2BHK | 1 | Tower E | 13 |
| 2BHK | 1 | Tower E | 13 |
| 2BHK | 1 | Tower E | 13 |
| 2BHK | 1 | Tower E | 13 |
| 1BHK | 1 | Tower E | 14 |
| 2BHK | 1 | Tower E | 14 |
| 2BHK | 1 | Tower E | 14 |
| 2BHK | 1 | Tower E | 14 |
| 2BHK | 1 | Tower E | 14 |
| 2BHK | 1 | Tower E | 14 |
| 2BHK | 1 | Tower D | 0 |
| 2BHK | 1 | Tower D | 0 |
| 3BHK | 1 | Tower D | 0 |
| 1BHK | 1 | Tower D | 0 |
| 2BHK | 1 | Tower D | 0 |
| 4BHK | 1 | Tower D | 1 |
| 2BHK | 1 | Tower D | 1 |
| 3BHK | 1 | Tower D | 1 |
| 1BHK | 1 | Tower D | 1 |
| 2BHK | 1 | Tower D | 1 |
| 2BHK | 1 | Tower D | 1 |
| 4BHK | 1 | Tower D | 2 |
| 2BHK | 1 | Tower D | 2 |
| 3BHK | 1 | Tower D | 2 |
| 1BHK | 1 | Tower D | 2 |
| 2BHK | 1 | Tower D | 2 |
| 2BHK | 1 | Tower D | 2 |
| 4BHK | 1 | Tower D | 3 |
| 2BHK | 1 | Tower D | 3 |
| 3BHK | 1 | Tower D | 3 |
| 1BHK | 1 | Tower D | 3 |
| 2BHK | 1 | Tower D | 3 |
| 2BHK | 1 | Tower D | 3 |
| 4BHK | 1 | Tower D | 4 |
| 2BHK | 1 | Tower D | 4 |
| 3BHK | 1 | Tower D | 4 |
| 1BHK | 1 | Tower D | 4 |
| 2BHK | 1 | Tower D | 4 |
| 2BHK | 1 | Tower D | 4 |
| 4BHK | 1 | Tower D | 5 |
| 2BHK | 1 | Tower D | 5 |
| 3BHK | 1 | Tower D | 5 |
| 1BHK | 1 | Tower D | 5 |
| 2BHK | 1 | Tower D | 5 |
| 2BHK | 1 | Tower D | 5 |
| 4BHK | 1 | Tower D | 6 |
| 2BHK | 1 | Tower D | 6 |
| 3BHK | 1 | Tower D | 6 |
| 1BHK | 1 | Tower D | 6 |
| 2BHK | 1 | Tower D | 6 |
| 2BHK | 1 | Tower D | 6 |
| 4BHK | 1 | Tower D | 7 |
| 2BHK | 1 | Tower D | 7 |
| 3BHK | 1 | Tower D | 7 |
| 1BHK | 1 | Tower D | 7 |
| 2BHK | 1 | Tower D | 7 |
| 2BHK | 1 | Tower D | 7 |
| 4BHK | 1 | Tower D | 8 |
| 2BHK | 1 | Tower D | 8 |
| 3BHK | 1 | Tower D | 8 |
| 1BHK | 1 | Tower D | 8 |
| 2BHK | 1 | Tower D | 8 |
| 2BHK | 1 | Tower D | 8 |
| 4BHK | 1 | Tower D | 9 |
| 2BHK | 1 | Tower D | 9 |
| 3BHK | 1 | Tower D | 9 |
| 1BHK | 1 | Tower D | 9 |
| 2BHK | 1 | Tower D | 9 |
| 2BHK | 1 | Tower D | 9 |
| 4BHK | 1 | Tower D | 10 |
| 2BHK | 1 | Tower D | 10 |
| 3BHK | 1 | Tower D | 10 |
| 1BHK | 1 | Tower D | 10 |
| 2BHK | 1 | Tower D | 10 |
| 2BHK | 1 | Tower D | 10 |
| 4BHK | 1 | Tower D | 11 |
| 2BHK | 1 | Tower D | 11 |
| 3BHK | 1 | Tower D | 11 |
| 1BHK | 1 | Tower D | 11 |
| 2BHK | 1 | Tower D | 11 |
| 2BHK | 1 | Tower D | 11 |
| 4BHK | 1 | Tower D | 12 |
| 2BHK | 1 | Tower D | 12 |
| 3BHK | 1 | Tower D | 12 |
| 1BHK | 1 | Tower D | 12 |
| 2BHK | 1 | Tower D | 12 |
| 2BHK | 1 | Tower D | 12 |
| 4BHK | 1 | Tower D | 13 |
| 2BHK | 1 | Tower D | 13 |
| 3BHK | 1 | Tower D | 13 |
| 1BHK | 1 | Tower D | 13 |
| 2BHK | 1 | Tower D | 13 |
| 2BHK | 1 | Tower D | 13 |
| 4BHK | 1 | Tower D | 14 |
| 2BHK | 1 | Tower D | 14 |
| 3BHK | 1 | Tower D | 14 |
| 1BHK | 1 | Tower D | 14 |
| 2BHK | 1 | Tower D | 14 |
| 2BHK | 1 | Tower D | 14 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-01-01 | |
|---|---|---|
| Proposed completion | 2028-12-31 | |
| Revised completion | 2029-09-30 |
Extensions
| Valid to |
|---|
| 2029-09-30 |
| 2029-09-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Dr Jerry Vincent Dias | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Karnataka Bank Ltd. | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://mahitikanaja.karnataka.gov.in/Rera/api/Rera/ProjectViewDetails
- https://rera.karnataka.gov.in/projectDetails
- https://rera.karnataka.gov.in/projectViewDetails
- https://rera.karnataka.gov.in/viewAllProjects?language=en
- Certificate · Sign in to download
- Other · Sign in to download
- Commencement Certificate
- Approved Building/Plotting Plan
- Approved Layout Plan
- Land documents and Location · Sign in to download
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Performa of Allotment Letter · Sign in to download
- Brochure of Current Project · Sign in to download
- All NOCs from Authority
- Project Specification · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Cash Flow Statement · Sign in to download
- Cash Flow Statement · Sign in to download
- Auditor's Report · Sign in to download
- Auditor's Report · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Declaration (Form B) · Sign in to download
- Prospectus/Brochure · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- NOC issued by the Fire Force department after completion of work
- Occupancy Certificate
- Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of Karnataka · Sign in to download
- f operation for lifts issued by the Chief of Department of Electrical inspectorate Government of Karnataka · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Architect certificate for having completed the work(in format no 5) · Sign in to download
- Chartered Accountant certificate for having completed the work(in format no 4) · Sign in to download
- ht"> Chartered Accountant certificate for having completed the work(in format no 4) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- FORM 6
- FORM 6
- FORM 6
- FORM 4CC
- Registration certificate
- Registration certificate
- Registration Certificate
- Commencement Certificate
- All NOCs from Authority
- NOC issued by the Fire Force department after completion of work
- Occupancy Certificate
- Extension order