Overview

MAPPLE TREE

AARAMBH INFRAVENTURES · RAIPUR
Units67
Booked25 of 67As of 2023-03-31
Construction progress100%As of 2023-03-31
Completion2023-07-30Revised · Proposed 2022-10-31
Registered on2018-06-20
Approvals6
Cases1

Sections

Property title & search report
Approvals6 approvals
Disputes & cases1 case
Contract & costs2 cost heads · 19 quarters
Technical report
Site & area3 site details · 12 unit types
Construction & progress4 progress details · 19 quarters
Developer & finance
Developer4 developer details
The evidence
Sources140 documents · 12 source links

Registration

Registration

PromoterAARAMBH INFRAVENTURES
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA200618000256
Registered on2018-06-20
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2022-10-31
Revised completion2023-07-30