Overview
MAPSKO MOUNT VILLE PHASE - II
MAPSKO BUILDERS PVT LTD · Gurugram
Units56
Completion2027-12-31Proposed
Registered on2023-02-02
Valid to2029-01-31
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 5 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 42 documents · 2 source links |
Registration
Registration
| Promoter | MAPSKO BUILDERS PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/689/421/2023/33 DATED 02.02.2023 | |
| Registered on | 2023-02-02 | |
| Valid to | 2029-01-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2027-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 38 of 2012 | Town & Country Planning Department | |
| Layout Plan | 2022-12-27 | ||
| Building Plan | 2022-12-27 | ||
| I. REVISED BUILDING PLAN IN PRINCIPAL APPROVAL | 2022-09-19 | ||
| II. REVISED BUILDING PLAN | 2022-12-27 | ||
| III. LICENCE | 2012-04-22 | ||
| IV. ZONING PLAN | 2012-04-24 | ||
| V. BUILDING PLAN | 2012-09-20 | ||
| VI. ENVIRONMENT CLEARANCE | 2013-09-06 | ||
| VII. AIRPORT | 2012-04-19 | ||
| VIII. FOREST | 2013-01-30 | ||
| IX. FIRE FIGHTING | 2013-03-02 | ||
| X. REVISED ENVIRONMENT CLEARANCE | 2022-10-13 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,00,32,000 | |
|---|---|---|
| Construction | ₹50,01,12,000 | |
| Total | ₹85,97,03,000.0000001 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1.75 | |
|---|---|---|
| Units | 56 |
Unit types
| Apartment/Shops/Other Buildings | 183.987 | 52 |
| Apartment/Shops/Other Buildings | 445.195 | 1 |
| Apartment/Shops/Other Buildings | 788.975 | 1 |
| Apartment/Shops/Other Buildings | 754.009 | 1 |
| Apartment/Shops/Other Buildings | 549.133 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-02-01 | |
|---|---|---|
| Proposed completion | 2027-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAPSKO BUILDERS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2149
- Registration Certificate · 2023-02-02
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2023-01-20 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2023-01-20
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2023-01-20 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2023-01-20
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2023-01-20
- FLOOR PLAN EWS · 2023-06-23
- ENVIORNMENT CLEARANCE MOUNT VILLE · 2023-06-23
- SEWERAGE PLAN · 2023-06-23
- ZONING PLAN · 2023-06-23
- AIRPORT NOC RENEWAL UPTO 06-07-2030 · 2023-06-23
- CA CERTIFICATE FOR PROJECT COST INCURRED TILL DATE · 2023-06-23 · Sign in to download
- REVISED ENVIORNMENT CLEARANCE MOUNT VILLE · 2023-06-23
- BR-III MMV REVISED · 2023-06-23 · Sign in to download
- ELEVATION AND SECTION CLUSTER 4 · 2023-06-23 · Sign in to download
- FLOOR PLAN, SECTION AND ELEVATION V3 · 2023-06-23
- FLOOR PLAN AND ELEVATION CLUSTER 4 · 2023-06-23
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2023-06-23
- WATER SUPPLY PLAN · 2023-06-23
- FLOOR PLAN, SECTION AND ELEVATION V2 · 2023-06-23
- ROAD LAYOUT · 2023-06-23 · Sign in to download
- DEMARCATION PLAN · 2023-06-23
- RECYCLED WATER SUPPLY PLAN · 2023-06-23
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2023-06-23
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2023-06-23 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2023-06-23 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2023-06-23 · Sign in to download
- ASSURANCE CONSTRUCTION WATER · 2023-06-23 · Sign in to download
- ASSURANCE SEWERAGE CONNECTION · 2023-06-23 · Sign in to download
- ASSURANCE STROM WATER · 2023-06-23 · Sign in to download
- ASSURANCE WATER · 2023-06-23 · Sign in to download
- BANK UNDERTAKING · 2023-06-23 · Sign in to download
- BASEMENT PLAN WITH AREA · 2023-06-23
- DRAINAGE PLAN · 2023-06-23
- FIRE LAYOUT · 2023-06-23 · Sign in to download
- FLOOR PLAN CLUSTER 4 · 2023-06-23
- FLOOR PLAN, SECTION AND ELEVATION SCHOOL1 · 2023-06-23
- FLOOR PLAN, SECTION AND ELEVATION V1 · 2023-06-23
- OC · 2023-06-23 · Sign in to download
- SECTION AND ELEVATION V3 · 2023-06-23 · Sign in to download
- SITE PLAN · 2023-06-23
- Change in the name of group housing project from "Mapsko Mount Ville Phase-II" to " Mapsko The Icon-79" · 2023-07-18 · Sign in to download