MARUTI INFRA CITY PHASE- II

PARRGUN CHHABDA · DURG
Units220
Booked216 of 220As of 2022-06-30
Construction progress100%As of 2022-06-30
Completion2023-02-08Revised · Proposed 2020-11-08
Registered on2018-06-30
Approvals3
Cases2

Sections

Property title & search report
Approvals3 approvals
Disputes & cases2 cases
Contract & costs2 cost heads · 16 quarters
Technical report
Site & area3 site details · 1 unit type
Construction & progress4 progress details · 16 quarters
Developer & finance
Developer4 developer details
The evidence
Sources92 documents · 10 source links

Registration

Registration

PromoterPARRGUN CHHABDA
DistrictDURG
RegulatorCG RERA
Registration numberPCGRERA300618000422
Registered on2018-06-30
Project typePlotted Development
Status (as filed)Ongoing
Proposed completion2020-11-08
Revised completion2023-02-08