Overview
MAXON PLAZA
LEADER INFRASTRUCTURES PRIVATE LIMITED · Shahid Bhagat Singh Nagar (Nawanshahr)
Units67
Completion2026-10-18Proposed
Valid to2026-10-18
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 20 unit types |
| Construction & progress | 2 progress details · 7 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 19 source links |
Registration
Registration
| Promoter | LEADER INFRASTRUCTURES PRIVATE LIMITED | |
|---|---|---|
| District | Shahid Bhagat Singh Nagar (Nawanshahr) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SBS83-PC0271 | |
| Valid to | 2026-10-18 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2026-10-18 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | Permissions (Received) | 2024-05-09 |
| License as Promoter from competent Authority | Permissions (Received) | 2023-03-27 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2022-12-19 |
| NOC from NHAI/ PWD | Permissions (Received) | 2022-12-12 |
| Other Document (NOC from Forest Department) | Permissions (Received) | 2023-10-09 |
| Other Document (NOC reg. Sewerage, Water Supply and Solid Waste) | Permissions (Received) | 2023-10-13 |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2024-02-26 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹5,70,45,315 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,626.67 | |
|---|---|---|
| Units | 67 |
Unit types
| Shop No.1 to 12 | 429.13 | 12 | COMMERCIAL SHOPS |
| Shop No.13 | 40.45 | 1 | COMMERCIAL SHOPS |
| Shop No.14 | 39.87 | 1 | COMMERCIAL SHOPS |
| Shop No.15 | 39.25 | 1 | COMMERCIAL SHOPS |
| Shop No.16 | 38.67 | 1 | COMMERCIAL SHOPS |
| Shop No.17 | 38.08 | 1 | COMMERCIAL SHOPS |
| Shop No.18 | 37.5 | 1 | COMMERCIAL SHOPS |
| Shop No.19 | 36.92 | 1 | COMMERCIAL SHOPS |
| Shop No.20 | 36.34 | 1 | COMMERCIAL SHOPS |
| Shop No.21 | 35.76 | 1 | COMMERCIAL SHOPS |
| Shop No.22 | 35.18 | 1 | COMMERCIAL SHOPS |
| Shop No.23 | 34.6 | 1 | COMMERCIAL SHOPS |
| Shop No.24 | 34.02 | 1 | COMMERCIAL SHOPS |
| Shop No.25 | 33.44 | 1 | COMMERCIAL SHOPS |
| Shop No.26 | 32.86 | 1 | COMMERCIAL SHOPS |
| Shop No.27 | 32.55 | 1 | COMMERCIAL SHOPS |
| Shop No.28 to 35 | 260.06 | 8 | COMMERCIAL SHOPS |
| Shop No.36 to 47 | 429.13 | 12 | COMMERCIAL SHOPS |
| Shop No.48 to 57 | 696.74 | 10 | COMMERCIAL SHOPS |
| Shop No.58 to 67 | 543.48 | 10 | COMMERCIAL SHOPS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-10-19 | |
|---|---|---|
| Proposed completion | 2026-10-18 |
Quarterly progress
| 2024-Q3 | 2024-10-19 |
| 2024-Q4 | 2025-01-07 |
| 2025-Q1 | 2025-04-10 |
| 2025-Q2 | 2025-07-11 |
| 2025-Q3 | 2025-10-15 |
| 2025-Q4 | 2026-01-14 |
| 2026-Q1 | 2026-04-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | LEADER INFRASTRUCTURES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Axis Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11876&inPromoter_ID=2759&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-05-09
- License as Promoter from competent Authority · 2023-03-27
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-12-19
- NOC from NHAI/ PWD · 2022-12-12
- Other Document (B.G. for Rs.3368490 submitted to PSPCL Deptt.) · 2024-04-18 · Sign in to download
- Other Document (DRAINAGE CUM MINING OFFICER) · 2023-10-10 · Sign in to download
- Other Document (NOC from Forest Department) · 2023-10-09
- Other Document (NOC reg. Sewerage, Water Supply and Solid Waste) · 2023-10-13
- Pollution Clearance from Punjab Pollution Control Board · 2024-02-26
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2024-05-09
- License as Promoter from competent Authority · 2023-03-27
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-12-19
- NOC from NHAI/ PWD · 2022-12-12
- Other Document (NOC from Forest Department) · 2023-10-09
- Other Document (NOC reg. Sewerage, Water Supply and Solid Waste) · 2023-10-13
- Pollution Clearance from Punjab Pollution Control Board · 2024-02-26
- 2024-Q3 · 2024-10-19
- 2024-Q4 · 2025-01-07
- 2025-Q1 · 2025-04-10
- 2025-Q2 · 2025-07-11
- 2025-Q3 · 2025-10-15
- 2025-Q4 · 2026-01-14
- 2026-Q1 · 2026-04-10