Overview
MAYFAIR AVANTIKA
MAYFAIR DEVELOPERS AND BUILDERS AND PURABI KUMAR · KAMRUP METRO
Units56
Completion2030-04-10Proposed
Registered on2025-06-18
Valid to2030-04-10
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 8 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 24 documents · 5 source links |
Registration
Registration
| Promoter | MAYFAIR DEVELOPERS AND BUILDERS AND PURABI KUMAR | |
|---|---|---|
| District | KAMRUP METRO | |
| Regulator | RERA Assam | |
| Registration number | RERAA KM 49 OF 2025-2026 | |
| Registered on | 2025-06-18 | |
| Valid to | 2030-04-10 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2030-04-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | |||
| Building Plan | |||
| NOC/Building Permit | BUILDING PERMIT BY GMC AND PLANNING PERMIT BY GMDA | 2024-05-29 | 2026-05-29 |
| I. BUILDING PERMIT BY GMC | 2024-05-29 | ||
| II. PLANNING PERMIT BY GMDA | 2024-02-07 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹16,81,40,332 | |
| Total | ₹22,96,96,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,408.92 | |
|---|---|---|
| Units | 56 |
Unit types
| 3 | 112.73 | 3 |
| 3 | 91.46 | 13 |
| 3 | 81.3 | 8 |
| 3 | 77.95 | 1 |
| 3 | 83.39 | 8 |
| 3 | 78.04 | 7 |
| 2 | 58.01 | 8 |
| 2 | 59.36 | 8 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-05-29 | |
|---|---|---|
| Proposed completion | 2030-04-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAYFAIR DEVELOPERS AND BUILDERS AND PURABI KUMAR | |
|---|---|---|
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/2212
- https://rera.assam.gov.in/view_project/searchprojectDetail/2212
- Registration Certificate
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2024-11-07 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2024-11-07 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2024-11-16 · Sign in to download
- AUDITED BALANCE SHEET OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2024-11-16 · Sign in to download
- POWER OF ATTORNEY · 2024-11-07 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2024-11-16 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2024-11-16 · Sign in to download
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2024-11-16 · Sign in to download
- PLANNING PERMIT FROM COMPETENT AUTHORITY · 2024-11-16
- FIRE NOC · 2024-11-16
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2024-11-16 · Sign in to download
- PLAN OF DEVELOPMENT WORKS · 2024-11-16
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2024-11-16 · Sign in to download
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2024-11-16 · Sign in to download
- CARPET AREA AND PARKING AREA DETAILS · 2024-11-16 · Sign in to download
- FORM B, DULY NOTARIZED · 2024-11-16 · Sign in to download
- LETTER OF AUTHORIZATION FOR AUTHORIZED SIGNATORY · 2024-11-16 · Sign in to download
- Other · 2024-11-16 · Sign in to download
- Project application order/letter · 2025-06-06 · Sign in to download
- Project application order/letter · 2025-05-27 · Sign in to download
- Project application order/letter · 2025-03-27 · Sign in to download
- Project application order/letter · 2025-02-28 · Sign in to download