Overview
MEENA ENCLAVE
BUDHA HOMES & DEVELOPERS · Patna
Units12
Completion2021-11-14Proposed
Registered on2018-12-18
Approvals1
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 3 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 10 source links |
Registration
Registration
| Promoter | BUDHA HOMES & DEVELOPERS | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00548-1/399/R-309/2018 | |
| Registered on | 2018-12-18 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2021-11-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA/CC-1082/2020 Execution Case No. 416/2024 | RERA Bihar | Pending |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,30,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 583 | |
|---|---|---|
| Built-up (m²) | 992.03 | |
| FAR | 1.68 | |
| Towers | 1 | |
| Units | 12 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 5 | MEENA ENCLAVE |
| 2 BHK | 7 | MEENA ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-05-15 | |
|---|---|---|
| Proposed completion | 2021-11-14 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2022-Q2 | 2022-08-06 |
| 2021-Q4 | 2022-08-08 |
| 2021-Q3 | 2022-08-08 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BUDHA HOMES & DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | IDBI Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=digha%2C+Patna%2C+Bihar%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP276201800548-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP276201800548-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2022-2023 · 2022-08-06
- Q3-Oct to Dec / 2021-2022 · 2022-08-08
- Q2-Jul to Sep / 2021-2022 · 2022-08-08
- Case proceeding RERA/CC-1082/2020 Execution Case No. 416/2024 · 2025-07-15 · Sign in to download
- Case proceeding RERA/CC-1082/2020 Execution Case No. 416/2024 · 2026-01-20 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- RERA/CC-1082/2020 Execution Case No. 416/2024 · Sign in to download
- 2022-Q2 · 2022-08-06
- 2021-Q4 · 2022-08-08
- 2021-Q3 · 2022-08-08