Overview
MELLOW SKYWATCH
MELLOW FOUNDATIONS BUILDERS AND DEVELOPERS PVT LTD · CALICUT
Units49
Booked49 of 49
Construction progress100%
Completion2020-06-30Proposed
Registered on2022-07-19
Approvals2
Cases1
Complaints1
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 1 case · 1 project complaint |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 3 progress details · 2 quarters |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 4 documents · 6 source links |
Registration
Registration
| Promoter | MELLOW FOUNDATIONS BUILDERS AND DEVELOPERS PVT LTD | |
|---|---|---|
| District | Kozhikode | |
| Locality | CALICUT | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/152/2021 | |
| Registered on | 2022-07-19 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2020-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | TP1/10/86695/2017 | 2017-10-20 | 2020-10-20 | KOZHIKODE CORPORATION |
| Development Permit | TP/10/86695/2017 | 2017-10-20 | 2020-10-20 | KOZHIKODE CORPORATION |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind |
|---|---|---|
| 267/2021 | K-RERA Kerala | Complaint |
Complaints & cases
| Cases | 1 | |
|---|---|---|
| Project complaints | 1 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,874 | |
|---|---|---|
| Built-up (m²) | 6,365.68 | |
| Towers | 0 | |
| Units | 49 | |
| Booked | 49 |
Unit types
| 2BHK | 12 | 12 | MELLOW SKYWATCH |
| 2BHK | 12 | 12 | MELLOW SKYWATCH |
| 2BHK | 12 | 12 | MELLOW SKYWATCH |
| 3BHK | 12 | 12 | MELLOW SKYWATCH |
| 3BHK | 1 | 1 | MELLOW SKYWATCH |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| Start | 1900-01-01 | |
| Proposed completion | 2020-06-30 |
Quarterly progress
| Quarter |
|---|
| 2021-2022 Q3 |
| 2021-2022 Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MELLOW FOUNDATIONS BUILDERS AND DEVELOPERS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF BARODA | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | JOSE THOMAS ASSOCIATES |
| Engineer | JTA ASSOCIATES |
| CA | MOHANAN AND MOHAN ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/complaint-list?ruling_by=all&page=73
- https://rera.kerala.gov.in/projects/10724
- https://rera.kerala.gov.in/projects?district=591&page=4
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=OcY3tBPcaweaD5deUXjZtXi6xYRZy4EhqHvtt2tY5TB6jN%2FUxAuTiOg8ZgS03kcyqPoETSox4HHeYLdRi%2B0SkGPTVTKu5KCMV9zhk3fFnJrBEWA1Kf4wQIappuBzg39BxxAB4DuXrbANc9o%2FNmXJpHWBdw4k5F6nuQtDov6LCcTxiEFwwwOncg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=10724&Division=1&UserID=30914&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2022-07-19
- Final Fire NOC · 2022-04-27