Overview
MELODY OF LIFE
Manglam Infra · Sahibzada Ajit Singh Nagar (Mohali)
Units162
Completion2028-01-31Proposed
Valid to2028-01-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 11 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 34 documents · 22 source links |
Registration
Registration
| Promoter | Manglam Infra | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0971 | |
| Valid to | 2028-01-31 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-01-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2022-11-15 |
| CLU Certificate | ||
| Electric Substation NOC | 2023-10-03 | |
| Environment Clearance certificate/ NOC | 2023-07-18 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Clearances (Received) | 2023-01-27 |
| Other Document (Drainage NOC) | 2024-02-27 | |
| Other Document (Sewerage NOC) | Clearances (Received) | 2023-01-25 |
| Other Document (Solid Waste NOC) | Clearances (Received) | 2023-01-23 |
| Pollution Clearance from Punjab Pollution Control Board | 2023-10-23 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,05,35,52,908 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 18,731.3432 | |
|---|---|---|
| Towers | 5 | |
| Maximum floors | 15 | |
| Units | 162 |
Unit types
| 3 BHK Flats Plus Servant Plus Utility | 1,457.36 | 36 | TOWER-01 |
| 4 BHK Plus Servant Plus Study Plus Utility | 1,457.36 | 3 | TOWER-01 |
| 3 BHK Flats Plus Servant Plus Utility | 1,494.15 | 18 | TOWER-02 |
| 5BHK Plus Servant Room Plus Study Room Plus Utility | 1,494.15 | 9 | TOWER-02 |
| 4BHK Plus Servant Room Plus Study Room Plus Ultility | 1,336.96 | 3 | TOWER-02 |
| 5BHK Plus Servant Plus Utility | 1,722.42 | 2 | TOWER-03 |
| 4BHK Plus Servant Plus Utility | 1,722.42 | 24 | TOWER-03 |
| 4BHK Plus Servant Plus Utility | 1,711.55 | 36 | TOWER-04 |
| 5BHK Plus Servant Plus Utility | 1,711.55 | 3 | TOWER-04 |
| 4 BHK Plus Servant Plus Utility | 1,251.55 | 8 | TOWER-05 |
| 3BHK Plus Utility | 2,101.48 | 20 | TOWER-05 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-01-31 | |
|---|---|---|
| Proposed completion | 2028-01-31 |
Quarterly progress
| 2024-Q2 | 2024-07-19 |
| 2024-Q3 | 2024-10-29 |
| 2024-Q4 | 2025-01-08 |
| 2025-Q1 | 2025-04-03 |
| 2025-Q2 | 2025-07-16 |
| 2025-Q3 | 2025-10-29 |
| 2025-Q4 | 2026-02-13 |
| 2026-Q1 | 2026-04-29 |
| 2026-Q2 | 2026-07-12 |
| 2026-Q3 | 2026-10-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Manglam Infra | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Bank of India | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11724&inPromoter_ID=2584&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2022-11-15
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2023-10-03
- Environment Clearance certificate/ NOC · 2023-07-18
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-01-27
- Other Document (Drainage NOC) · 2024-02-27
- Other Document (Sewerage NOC) · 2023-01-25
- Other Document (Solid Waste NOC) · 2023-01-23
- Pollution Clearance from Punjab Pollution Control Board · 2023-10-23
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2022-11-15
- CLU Certificate
- Electric Substation NOC · 2023-10-03
- Environment Clearance certificate/ NOC · 2023-07-18
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-01-27
- Other Document (Drainage NOC) · 2024-02-27
- Other Document (Sewerage NOC) · 2023-01-25
- Other Document (Solid Waste NOC) · 2023-01-23
- Pollution Clearance from Punjab Pollution Control Board · 2023-10-23
- 2024-Q2 · 2024-07-19
- 2024-Q3 · 2024-10-29
- 2024-Q4 · 2025-01-08
- 2025-Q1 · 2025-04-03
- 2025-Q2 · 2025-07-16
- 2025-Q3 · 2025-10-29
- 2025-Q4 · 2026-02-13
- 2026-Q1 · 2026-04-29
- 2026-Q2 · 2026-07-12
- 2026-Q3 · 2026-10-11