Overview
MET HIGHWAY MART
MODEL ECONOMIC TOWNSHIP LIMITED · Jhajjar
Units45
Completion2024-03-01Proposed
Valid to2027-06-01
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 5 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 2 source links |
Registration
Registration
| Promoter | MODEL ECONOMIC TOWNSHIP LIMITED | |
|---|---|---|
| District | Jhajjar | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-JJR-234-2021 | |
| Valid to | 2027-06-01 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-03-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 06 of 2018(01-02-2012), 16 of 2018 (23-02-2018), 129 of 2019(03-12-2024) and Delicensing done vide order LC-2473-B-JE(S)/2012/2164 dated 03.02.2019 | Town & Country Planning Department | |
| Layout Plan | 2019-12-04 | ||
| Building Plan | |||
| I. LICENSE NO. 6 OF 2012 | 2021-02-01 | ||
| II. LICENSE NO. 16 OF 2018 | 2018-02-23 | ||
| III. DELICENSING VIDE LC-3684-B/JE(MK)/2019/29885 | 2019-12-05 | ||
| IV. LICENSE NO.129 OF 2019 | 2019-12-04 | ||
| V. CONSENT TO ESTABLISH PERMISSION | 2020-01-21 | ||
| VI. ENVIRONMENT CLEARANCE | 2019-12-13 | ||
| VII. LAYOUT PLAN | 2019-12-04 | ||
| VIII. SITE PLAN | 2021-02-01 | ||
| IX. SITE PLAN (WITH SERVICES) | 2021-02-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,79,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹18,73,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 150 | |
|---|---|---|
| Units | 45 |
Unit types
| Plot | 9 | |
| Plot | 33 | |
| Plot | 1 | |
| Plot | 2 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-03-01 | |
|---|---|---|
| Proposed completion | 2024-03-01 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MODEL ECONOMIC TOWNSHIP LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 16 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/view_project/project_preview_open/1552
- Registration Certificate
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-02-11
- DEMARCATION PLAN · 2021-02-11
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-02-11 · Sign in to download
- LICENSE 16 OF 2018 · 2021-02-11
- LICENSE NO. 129 OF 2019 · 2021-02-11
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-02-11
- SITE PLAN · 2021-02-11
- ARCHITECTURE CONTROL SHEET · 2021-02-11 · Sign in to download
- DETAIL OF PERMISSIBLE FAR · 2021-02-11 · Sign in to download
- DETAIL OF COVERED AREA ACHIEVED FAR · 2021-02-11 · Sign in to download
- ROADS AND PAVEMENT PLAN · 2021-02-12
- WATER AND ELECT. SUPPLY, SEWERAGE AND GARBAGE DIS., STROM WATER DRAINAGE PLAN · 2021-02-12
- DELICENSING VIDE LC-3684-B/JE(MK)/2019/29885 · 2021-02-12
- CONSENT TO ESTABLISH PERMISSION · 2021-02-12 · Sign in to download
- ENVIRONMENT CLEARANCE · 2021-02-12
- SITE PLAN (WITH SERVICES) · 2021-02-12
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-02-12
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-02-12
- AUDITED FINANCIAL STATEMENTS FOR THE YEAR ENDING 31.03.2020 · 2021-02-12 · Sign in to download
- AUDITED FINANCIAL STATEMENTS FOR THE YEAR ENDING 31.03.2019 · 2021-02-12 · Sign in to download
- AUDITED FINANCIAL STATEMENTS FOR THE YEAR ENDING 31.03.2018 · 2021-02-12 · Sign in to download
- PROJECT REPORT · 2021-02-12 · Sign in to download
- APPROVAL OF STANDARD DESIGNS OF SCOS BY DTCP HARYANA · 2021-02-12
- PROJECT FEES PAYMENT CLARIFICATION. · 2021-02-12 · Sign in to download
- CORRIGENDUM · 2023-01-19 · Sign in to download
- extension uploaded · 2024-06-19 · Sign in to download
- Corrigendum of bank account change is uploaded. · 2024-12-12 · Sign in to download
- CORRIGENDUM · 2025-05-16 · Sign in to download
- Extension uploaded · 2025-11-03 · Sign in to download
- Extension Uploaded · 2026-06-23 · Sign in to download