Overview
METRO HEXA
M/S SHIVAY INFRA · RAIPUR
Units49
Booked49 of 49As of 2024-12-31
Construction progress100%As of 2024-12-31
Completion2023-12-28Revised · Proposed 2021-03-31
Registered on2018-04-16
Approvals3
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 19 quarters |
| Technical report | |
| Site & area | 3 site details · 49 unit types |
| Construction & progress | 4 progress details · 19 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 116 documents · 9 source links |
Registration
Registration
| Promoter | M/S SHIVAY INFRA | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA160418000007 | |
| Registered on | 2018-04-16 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2021-03-31 | |
| Revised completion | 2023-12-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2024-02473 | CG RERA | Complaint | Disposed | 2024-07-26 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,84,94,000 | |
|---|---|---|
| Construction | ₹29,64,31,078.3 |
Quarterly money flows
| 2018-Q3 | ₹11,000 |
| 2018-Q4 | ₹11,000 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹4,10,406.46 |
| 2019-Q3 | ₹11,934.46 |
| 2019-Q4 | ₹5,71,500 |
| 2020-Q1 | ₹8,99,600 |
| 2020-Q2 | ₹0.17 |
| 2020-Q3 | ₹16,43,000 |
| 2020-Q4 | ₹2,44,000 |
| 2021-Q1 | ₹20,95,000 |
| 2021-Q2 | ₹7,88,000 |
| 2021-Q3 | ₹2,31,000 |
| 2021-Q4 | ₹7,18,000 |
| 2022-Q1 | ₹3,02,000 |
| 2022-Q2 | ₹23,72,000 |
| 2022-Q3 | ₹30,000 |
| 2022-Q4 | ₹1,09,090 |
| 2024-Q4 | ₹960 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 49 | |
|---|---|---|
| Booked | 49 | |
| Booked as of | 2024-12-31 |
Unit types
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 1BHK | 50.16 | 1 | 1 |
| 1BHK | 50.16 | 1 | 1 |
| 1BHK | 50.16 | 1 | 1 |
| 1BHK | 50.16 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
| 3BHK | 200.78 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2024-12-31 | |
| Proposed completion | 2021-03-31 | |
| Revised completion | 2023-12-28 |
Quarterly progress
| 2018-Q3 | 0% |
| 2018-Q4 | 12% |
| 2019-Q1 | 32% |
| 2019-Q2 | 35% |
| 2019-Q3 | 41% |
| 2019-Q4 | 48% |
| 2020-Q1 | 50% |
| 2020-Q2 | 51% |
| 2020-Q3 | 53% |
| 2020-Q4 | 57% |
| 2021-Q1 | 45% |
| 2021-Q2 | 47% |
| 2021-Q3 | 0% |
| 2021-Q4 | 61% |
| 2022-Q1 | 62% |
| 2022-Q2 | 65% |
| 2022-Q3 | 65% |
| 2022-Q4 | 66% |
| 2024-Q4 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S SHIVAY INFRA | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTM=
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Engineer Certificate
- CA Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Final order · 2024-07-26 · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities
- SM-EXP-2024-02473 · Sign in to download