Overview
MIXED LAND USE COLONY FOR 14.4125 ACRES
MANGLAM MULTIPLEX PVT LTD · Gurugram
Units2,399
Completion2024-06-30Proposed
Registered on2017-06-14
Valid to2024-05-01
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 11 documents · 3 source links |
Registration
Registration
| Promoter | MANGLAM MULTIPLEX PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 01 OF 2017 DATED 14.06.2017 (SUPERSEDED BY GGM/688/420/2023/32 DATED 02.02.2023) | |
| Registered on | 2017-06-14 | |
| Valid to | 2024-05-01 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2024-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 15 of 2017 dated 2.05.2017 | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. LICENCE | 2017-05-02 | ||
| II. ZONING PLAN | 2017-05-02 | ||
| III. BUILDING PLAN | 2018-02-08 | ||
| IV. SERVICE PLAN ESTIMATES | 2019-03-11 | ||
| V. ARAVALI | 2014-12-12 | ||
| VI. FOREST | 2010-07-30 | ||
| VII. ELECTRICITY | 2017-05-03 | ||
| VIII. NOC FOR HEIGHT CLEARANCE | 2014-10-31 | ||
| IX. HARERA REGISTRATION NO. | 2017-06-14 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2024-05-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,45,40,00,000 | |
|---|---|---|
| Construction | ₹6,61,56,42,999.999999 | |
| Total | ₹27,06,46,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 2,05,888.046 | |
|---|---|---|
| Units | 2,399 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 1,50,491 | 2,399 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-11-15 | |
|---|---|---|
| Proposed completion | 2024-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MANGLAM MULTIPLEX PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LTD | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1182
- https://nominatim.openstreetmap.org/search?q=sector+65%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-06-14
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-02-12 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2020-02-12 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-01-28
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2020-01-28
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-01-28
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-01-28
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2020-01-28
- ZONING PLAN · 2020-01-28
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2020-01-28 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-02-07 · Sign in to download