Overview
MODEL INDUSTRIAL PARK, AMRITSAR
ALPHA CORP DEVELOPMENT PVT. LTD · Amritsar
Units531
Completion2022-12-10Proposed
Valid to2023-12-10
Approvals2
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details · 23 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 15 documents · 27 source links |
Registration
Registration
| Promoter | ALPHA CORP DEVELOPMENT PVT. LTD | |
|---|---|---|
| District | Amritsar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-ASR03-PM0143 | |
| Valid to | 2023-12-10 | |
| Project type | (1) Industrial (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2022-12-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date |
|---|---|
| Electric Substation NOC | 2020-07-10 |
| Environment Clearance certificate/ NOC | 2015-04-20 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum |
|---|---|
| nill | nill |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹2,07,26,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,33,310.9268 | |
|---|---|---|
| Units | 531 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| BAY SHOP/ SCO | 6,762.414 | 95 | MODEL INDUSTRIAL PARK AMRITSAR COMMERCIAL PLOTS |
| Industrial Plots | 3,27,381.997 | 436 | MODEL INDUSTRIAL PARK AMRITSAR INDUSTRIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-09-23 | |
|---|---|---|
| Proposed completion | 2022-12-10 |
Quarterly progress
| 2021-Q1 | 2021-05-06 |
| 2021-Q2 | 2021-07-05 |
| 2021-Q3 | 2021-10-06 |
| 2021-Q4 | 2022-01-12 |
| 2022-Q1 | 2022-04-05 |
| 2022-Q2 | 2022-07-19 |
| 2022-Q3 | 2022-11-22 |
| 2022-Q4 | 2023-01-25 |
| 2023-Q1 | 2023-05-02 |
| 2023-Q2 | 2023-07-10 |
| 2023-Q3 | 2023-10-10 |
| 2023-Q4 | 2024-01-12 |
| 2024-Q1 | 2024-04-15 |
| 2024-Q2 | 2024-07-03 |
| 2024-Q3 | 2024-10-14 |
| 2024-Q4 | 2025-01-15 |
| 2025-Q1 | 2025-04-16 |
| 2025-Q2 | 2025-07-27 |
| 2025-Q3 | 2025-10-30 |
| 2025-Q4 | 2026-01-23 |
| 2026-Q1 | 2026-05-04 |
| 2026-Q2 | 2026-07-27 |
| 2026-Q3 | 2026-10-28 |
Extensions
| Valid to |
|---|
| 2023-12-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ALPHA CORP DEVELOPMENT PVT. LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES Bank Limited | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | I M COST MANAGEMENT PVT LTD |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10936&inPromoter_ID=1765&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2016-11-23
- Commencement Certificate (Mega Project Category) · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Electric Substation NOC · 2020-07-10
- Environment Clearance certificate/ NOC · 2015-04-20
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Electric Substation NOC · 2020-07-10
- Environment Clearance certificate/ NOC · 2015-04-20
- 2021-Q1 · 2021-05-06
- 2021-Q2 · 2021-07-05
- 2021-Q3 · 2021-10-06
- 2021-Q4 · 2022-01-12
- 2022-Q1 · 2022-04-05
- 2022-Q2 · 2022-07-19
- 2022-Q3 · 2022-11-22
- 2022-Q4 · 2023-01-25
- 2023-Q1 · 2023-05-02
- 2023-Q2 · 2023-07-10
- 2023-Q3 · 2023-10-10
- 2023-Q4 · 2024-01-12
- 2024-Q1 · 2024-04-15
- 2024-Q2 · 2024-07-03
- 2024-Q3 · 2024-10-14
- 2024-Q4 · 2025-01-15
- 2025-Q1 · 2025-04-16
- 2025-Q2 · 2025-07-27
- 2025-Q3 · 2025-10-30
- 2025-Q4 · 2026-01-23
- 2026-Q1 · 2026-05-04
- 2026-Q2 · 2026-07-27
- 2026-Q3 · 2026-10-28