Overview
Mohali Citi Centre 3
KLG Infra · Sahibzada Ajit Singh Nagar (Mohali)
Units968
Completion2027-03-25Proposed
Valid to2027-03-25
Approvals11
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 22 unit types |
| Construction & progress | 2 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 38 documents · 30 source links |
Registration
Registration
| Promoter | KLG Infra | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PC0182 | |
| Valid to | 2027-03-25 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-03-25 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Amendments (Applied) | 2022-10-14 |
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2021-05-28 | |
| CLU Certificate | ||
| Electric Substation NOC | Legal Documents (To Be Applied) | 2022-11-29 |
| Environment Clearance certificate/ NOC | 2022-03-02 | |
| License as Promoter from competent Authority | 2021-07-16 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2022-05-24 |
| NOC from Mining Department | 2022-03-29 | |
| Other Document (Declaration for PSPCL NOC) | Legal Documents (To Be Applied) | 2022-11-29 |
| Pollution Clearance from Punjab Pollution Control Board | 2022-11-22 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum |
|---|---|
| GCNo 01612023 | Honble Chairman |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹5,27,97,67,228 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 39,578.26 | |
|---|---|---|
| Towers | 19 | |
| Maximum floors | 10 | |
| Units | 968 |
Unit types
| Showroom | 8,301.219 | 76 | BLOCK-A SECOND FLOOR |
| Shops | 2,634.936 | 70 | BLOCK-A SECOND FLOOR |
| Showroom | 5,532.212 | 78 | BLOCK-A GROUND FLOOR |
| Shops | 3,796.908 | 220 | BLOCK-A GROUND FLOOR |
| Showroom | 8,301.219 | 76 | BLOCK-A FIRST FLOOR |
| Shops | 2,634.936 | 70 | BLOCK-A FIRST FLOOR |
| Showroom | 7,047.813 | 58 | BLOCK-A THIRD FLOOR |
| Office | 7,047.813 | 58 | BLOCK-A FOURTH FLOOR |
| Office | 6,890.203 | 58 | BLOCK-A FIFTH FLOOR |
| Office | 6,890.203 | 58 | BLOCK-A SIXTH FLOOR |
| Office | 6,890.203 | 58 | BLOCK-A SEVENTH FLOOR |
| Showroom | 246.326 | 3 | BLOCK-B GF |
| Showroom | 325.06 | 3 | BLOCK-B 1ST FLOOR |
| Showroom | 325.06 | 3 | BLOCK-B 2ND FLOOR |
| Showroom | 325.06 | 3 | BLOCK-B 3RD FLOOR |
| Showroom | 325.06 | 3 | BLOCK-B 4TH FLOOR |
| Office | 325.06 | 3 | BLOCK-B 5TH FLOOR |
| Office | 325.06 | 3 | BLOCK-B 6TH FLOOR |
| Office | 325.06 | 3 | BLOCK-B 7TH FLOOR |
| Office | 325.06 | 3 | BLOCK-B 8TH FLOOR |
| Office | 325.06 | 3 | BLOCK-B 9TH FLOOR |
| Basement | 8,634.758 | 58 | BLOCK-A BASEMENT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-04-10 | |
|---|---|---|
| Proposed completion | 2027-03-25 |
Quarterly progress
| 2022-Q4 | 2023-11-13 |
| 2023-Q1 | 2023-11-13 |
| 2023-Q2 | 2023-11-13 |
| 2023-Q3 | 2023-11-13 |
| 2023-Q4 | 2024-05-22 |
| 2024-Q1 | 2024-05-23 |
| 2024-Q2 | 2024-10-15 |
| 2024-Q3 | 2024-10-15 |
| 2024-Q4 | 2025-01-15 |
| 2025-Q1 | 2025-04-12 |
| 2025-Q2 | 2025-07-13 |
| 2025-Q3 | 2025-10-11 |
| 2025-Q4 | 2026-01-13 |
| 2026-Q1 | 2026-04-14 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KLG Infra | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Kotak Mahindra Bank Limited | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11579&inPromoter_ID=2447&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2022-10-14
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2021-05-28
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2022-11-29
- Environment Clearance certificate/ NOC · 2022-03-02
- License as Promoter from competent Authority · 2021-07-16
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-05-24
- NOC from Mining Department · 2022-03-29
- Other Document (Declaration for PSPCL NOC) · 2022-11-29
- Pollution Clearance from Punjab Pollution Control Board · 2022-11-22
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2022-10-14
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2021-05-28
- CLU Certificate
- Electric Substation NOC · 2022-11-29
- Environment Clearance certificate/ NOC · 2022-03-02
- License as Promoter from competent Authority · 2021-07-16
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-05-24
- NOC from Mining Department · 2022-03-29
- Other Document (Declaration for PSPCL NOC) · 2022-11-29
- Pollution Clearance from Punjab Pollution Control Board · 2022-11-22
- 2022-Q4 · 2023-11-13
- 2023-Q1 · 2023-11-13
- 2023-Q2 · 2023-11-13
- 2023-Q3 · 2023-11-13
- 2023-Q4 · 2024-05-22
- 2024-Q1 · 2024-05-23
- 2024-Q2 · 2024-10-15
- 2024-Q3 · 2024-10-15
- 2024-Q4 · 2025-01-15
- 2025-Q1 · 2025-04-12
- 2025-Q2 · 2025-07-13
- 2025-Q3 · 2025-10-11
- 2025-Q4 · 2026-01-13
- 2026-Q1 · 2026-04-14
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-14