Overview
Mohali Hills
Emaar MGF Land Limited · Sahibzada Ajit Singh Nagar (Mohali)
Units2,989
Completion2020-06-30Proposed
Valid to2020-06-30
Approvals15
Sections
| Property title & search report | |
|---|---|
| Approvals | 15 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 17 unit types |
| Construction & progress | 2 progress details · 33 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 61 documents · 52 source links |
Registration
Registration
| Promoter | Emaar MGF Land Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0231 | |
| Valid to | 2020-06-30 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2020-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Electric Substation NOC | 2020-05-22 | |
| Environment Clearance certificate/ NOC | 2024-02-14 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2008-06-18 |
| License as Promoter from competent Authority | 2006-12-22 | |
| License as Promoter from competent Authority | 2006-12-22 | |
| License as Promoter from competent Authority | 2006-08-11 | |
| License as Promoter from competent Authority | 2008-01-22 | |
| License as Promoter from competent Authority | 2006-08-11 | |
| NOC from NHAI/ PWD | 2009-12-07 | |
| Other Document (Affidavit regarding submission of NOCs) | 2025-08-14 | |
| Other Document (Forest NOC) | 2024-08-09 | |
| Other Document (PSPCL applied.Drainage NOC shall submit in 60 days) | 2025-02-04 | |
| Pollution Clearance from Punjab Pollution Control Board | Clearances (Received) | 2018-03-26 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-04-25 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-05-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹13,36,59,67,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 25,84,009.141 | |
|---|---|---|
| Units | 2,989 |
Unit types
| 187 Sq Yards 281 Sq Yards 300 Sq Yards 400 Sq Yards 500 Sq Yards 700 Sq Yards 800 Sq Yards | 1,02,872.93 | 359 | SECTOR 98 105 108 |
| 150 Sq Yards 200 Sq Yards 250 Sq Yards 300 Sq Yards | 87,626.147 | 367 | SECTOR 109 |
| 150 Sq Yards to 600 Sq Yards | 12,422.75 | 37 | SECTOR 109 |
| 300 Sq Yards 350 400 Sq Yards 450 Sq Yards 500 Sq yards 600 sq Yards 750 Sq yards 800 Sq Yards | 59,197.817 | 232 | SECTOR 109 |
| 150 Sq Yards 200 Sq Yards 250 Sq Yards 300 Sq Yards | 87,626.147 | 367 | SECTOR 109 |
| 150 Sq Yards to 600 Sq Yards | 12,422.75 | 37 | SECTOR 109 |
| 150 Sq Yards 200 Sq Yards 250 Sq Yards 300 Sq Yards | 87,626.147 | 367 | SECTOR 109 |
| 150 Sq Yards to 600 Sq Yards | 12,422.75 | 37 | SECTOR 109 |
| 187 Sq Yards 281 Sq Yards 300 Sq Yards 400 Sq Yards 500 Sq Yards 700 Sq Yards 800 Sq Yards | 1,02,872.93 | 359 | SECTOR 98 105 108 |
| 187 Sq Yards 281 Sq Yards 300 Sq Yards 400 Sq Yards 500 Sq Yards 700 Sq Yards 800 Sq Yards | 1,02,872.93 | 359 | SECTOR 98 105 108 |
| 250 Sq Yards to 350 Sq Yards | 1,843.56 | 7 | SECTOR 104 |
| 150 Sq Yards to 350 Sq Yards | 1,043.21 | 4 | SECTOR 99 |
| 400 Sq Yards to 550 Sq Yards | 4,129.29 | 9 | SECTOR 105 |
| 200 Sq Yards to 300 Sq Yards | 599.4 | 2 | SECTOR 106 |
| 200 Sq Yards to 700 Sq Yards | 15,307.79 | 42 | SECTOR 108 |
| 150 Sq Yards 200 Sq Yards 250 Sq Yards 300 Sq Yards | 87,626.147 | 367 | SECTOR 109 |
| 150 Sq Yards to 600 Sq Yards | 12,422.75 | 37 | SECTOR 109 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2006-11-15 | |
|---|---|---|
| Proposed completion | 2020-06-30 |
Quarterly progress
| 2020-Q3 | 2020-12-05 |
| 2020-Q4 | 2021-01-14 |
| 2021-Q1 | 2021-04-14 |
| 2021-Q2 | 2021-07-14 |
| 2021-Q3 | 2021-10-21 |
| 2021-Q4 | 2022-01-06 |
| 2018-Q3 | 2022-01-13 |
| 2018-Q4 | 2022-01-14 |
| 2019-Q1 | 2022-01-14 |
| 2019-Q2 | 2022-01-14 |
| 2019-Q3 | 2022-01-14 |
| 2019-Q4 | 2022-01-14 |
| 2020-Q1 | 2022-01-14 |
| 2020-Q2 | 2022-01-14 |
| 2022-Q1 | 2022-04-06 |
| 2022-Q2 | 2022-07-05 |
| 2022-Q3 | 2022-10-06 |
| 2022-Q4 | 2023-01-10 |
| 2023-Q1 | 2023-04-06 |
| 2023-Q2 | 2023-07-07 |
| 2023-Q3 | 2023-10-07 |
| 2023-Q4 | 2024-01-15 |
| 2024-Q1 | 2024-04-02 |
| 2024-Q2 | 2024-07-04 |
| 2024-Q3 | 2024-10-07 |
| 2024-Q4 | 2025-01-08 |
| 2025-Q1 | 2025-04-11 |
| 2025-Q2 | 2025-07-08 |
| 2025-Q3 | 2025-10-14 |
| 2025-Q4 | 2026-01-12 |
| 2026-Q1 | 2026-04-13 |
| 2026-Q2 | 2026-07-13 |
| 2026-Q3 | 2026-10-13 |
Extensions
| Valid to |
|---|
| 2025-07-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Emaar MGF Land Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | Others | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10692&inPromoter_ID=1571&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Borewell Registration certificate from Central Ground Water Authority · 2017-03-27
- Commencement Certificate (Mega Project Category) · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Electric Substation NOC · 2020-05-22
- Environment Clearance certificate/ NOC · 2024-02-14
- Environment Clearance certificate/ NOC · 2008-06-18
- License as Promoter from competent Authority · 2006-12-22
- License as Promoter from competent Authority · 2006-12-22
- License as Promoter from competent Authority · 2006-08-11
- License as Promoter from competent Authority · 2008-01-22
- License as Promoter from competent Authority · 2006-08-11
- NOC from NHAI/ PWD · 2009-12-07
- Other Document (Architect Certificate regd. AAI) · 2025-08-14 · Sign in to download
- Other Document (Forest NOC) · 2024-08-09
- Other Document (PSPCL applied.Drainage NOC shall submit in 60 days) · 2025-02-04
- Other Document (Road Access from GMADA) · 2010-02-03 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2018-03-26
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-25
- Pollution Clearance from Punjab Pollution Control Board · 2024-05-30
- Consent details of actual owner of Land · Sign in to download
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- Electric Substation NOC · 2020-05-22
- Environment Clearance certificate/ NOC · 2024-02-14
- Environment Clearance certificate/ NOC · 2008-06-18
- License as Promoter from competent Authority · 2006-12-22
- License as Promoter from competent Authority · 2006-12-22
- License as Promoter from competent Authority · 2006-08-11
- License as Promoter from competent Authority · 2008-01-22
- License as Promoter from competent Authority · 2006-08-11
- NOC from NHAI/ PWD · 2009-12-07
- Other Document (Affidavit regarding submission of NOCs) · 2025-08-14
- Other Document (Forest NOC) · 2024-08-09
- Other Document (PSPCL applied.Drainage NOC shall submit in 60 days) · 2025-02-04
- Pollution Clearance from Punjab Pollution Control Board · 2018-03-26
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-25
- Pollution Clearance from Punjab Pollution Control Board · 2024-05-30
- Extension order · Sign in to download
- 2020-Q3 · 2020-12-05
- 2020-Q4 · 2021-01-14
- 2021-Q1 · 2021-04-14
- 2021-Q2 · 2021-07-14
- 2021-Q3 · 2021-10-21
- 2021-Q4 · 2022-01-06
- 2018-Q3 · 2022-01-13
- 2018-Q4 · 2022-01-14
- 2019-Q1 · 2022-01-14
- 2019-Q2 · 2022-01-14
- 2019-Q3 · 2022-01-14
- 2019-Q4 · 2022-01-14
- 2020-Q1 · 2022-01-14
- 2020-Q2 · 2022-01-14
- 2022-Q1 · 2022-04-06
- 2022-Q2 · 2022-07-05
- 2022-Q3 · 2022-10-06
- 2022-Q4 · 2023-01-10
- 2023-Q1 · 2023-04-06
- 2023-Q2 · 2023-07-07
- 2023-Q3 · 2023-10-07
- 2023-Q4 · 2024-01-15
- 2024-Q1 · 2024-04-02
- 2024-Q2 · 2024-07-04
- 2024-Q3 · 2024-10-07
- 2024-Q4 · 2025-01-08
- 2025-Q1 · 2025-04-11
- 2025-Q2 · 2025-07-08
- 2025-Q3 · 2025-10-14
- 2025-Q4 · 2026-01-12
- 2026-Q1 · 2026-04-13
- 2026-Q2 · 2026-07-13
- 2026-Q3 · 2026-10-13