MONT ZION

M/s. CHURCHILL & JERRY INFRASTRUCTURE · Bengaluru Urban
Units84
Completion2022-09-30Revised · Proposed 2021-12-31
Registered on2019-01-31
Valid to2022-09-30
Approvals2
Complaints0

Sections

Property title & search report
Approvals2 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads
Technical report
Site & area5 site details · 84 unit types
Construction & progress3 progress details · 2 extensions
Developer & finance
Developer4 developer details
The evidence
Sources46 documents · 9 source links

Registration

Registration

PromoterM/s. CHURCHILL & JERRY INFRASTRUCTURE
DistrictBengaluru Urban
RegulatorK-RERA
Registration numberPRM/KA/RERA/1251/309/PR/190131/002325
Registered on2019-01-31
Valid to2022-09-30
Project typeResidential/Group Housing
Status (as filed)APPROVED
Proposed completion2021-12-31
Revised completion2022-09-30