Overview
MOTI KUNWAR COMPLEX
MAA TARA INFRA · Patna
Units118
Completion2024-04-15Proposed
Registered on2022-03-17
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 4 unit types |
| Construction & progress | 2 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 18 source links |
Registration
Registration
| Promoter | MAA TARA INFRA | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP82543-1/184/R-1307/2022 | |
| Registered on | 2022-03-17 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2024-04-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc. |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,40,75,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,782.43 | |
|---|---|---|
| Built-up (m²) | 4,465.03 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 118 |
Unit types
| Assisted Living Room | 42 | MOTI KUNWAR COMPLEX |
| Convenience Store | 51 | MOTI KUNWAR COMPLEX |
| 3 BHK | 20 | MOTI KUNWAR COMPLEX |
| 1 BHK | 5 | MOTI KUNWAR COMPLEX |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-12-10 | |
|---|---|---|
| Proposed completion | 2024-04-15 |
Quarterly progress
| 2025-Q1 | 2025-05-14 |
| 2024-Q4 | 2025-02-12 |
| 2024-Q3 | 2024-10-16 |
| 2024-Q2 | 2024-10-16 |
| 2024-Q1 | 2024-10-16 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2024-07-25 |
| 2022-Q4 | 2023-02-05 |
| 2022-Q3 | 2023-02-05 |
| 2022-Q2 | 2023-02-05 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAA TARA INFRA | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP12022021182543-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP12022021182543-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2024-2025 · 2025-05-14
- Q3-Oct to Dec / 2024-2025 · 2025-02-12
- Q2-Jul to Sep / 2024-2025 · 2024-10-16
- Q1-Apr to Jun / 2024-2025 · 2024-10-16
- Q4-Jan to Mar / 2023-2024 · 2024-10-16
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2023-02-05
- Q2-Jul to Sep / 2022-2023 · 2023-02-05
- Q1-Apr to Jun / 2022-2023 · 2023-02-05
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Notice of Commencement
- 2025-Q1 · 2025-05-14
- 2024-Q4 · 2025-02-12
- 2024-Q3 · 2024-10-16
- 2024-Q2 · 2024-10-16
- 2024-Q1 · 2024-10-16
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2023-02-05
- 2022-Q3 · 2023-02-05
- 2022-Q2 · 2023-02-05