Overview
MUIRWOODS ECOCITY EXTENSION - 7
THE GREATER PUNJAB OFFICERS CO-OP HOUSE BUILDING SOCIETY LTD · Sahibzada Ajit Singh Nagar (Mohali)
Units94
Completion2029-04-23Proposed
Valid to2029-04-23
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 31 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 20 source links |
Registration
Registration
| Promoter | THE GREATER PUNJAB OFFICERS CO-OP HOUSE BUILDING SOCIETY LTD | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS80-PR0914 | |
| Valid to | 2029-04-23 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-04-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance certificate/ NOC | Clearances (Received) | 2023-12-28 |
| License as Promoter from competent Authority | 2020-12-02 | |
| Other Document (Approved CLU) | 2022-03-07 | |
| Other Document (NOC AIR) | Clearances (Received) | 2023-09-18 |
| Other Document (NOC FOREST) | Clearances (Received) | 2023-09-15 |
| Other Document (NOC PSPCL) | Clearances (Received) | 2023-12-27 |
| Pollution Clearance from Punjab Pollution Control Board | Clearances (Received) | 2023-12-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹20,03,85,820 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 43,382.3 | |
|---|---|---|
| Units | 94 |
Unit types
| PLOT | 260.13 | 4 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 116.13 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 262.36 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 263.84 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 269.2 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 274.99 | 3 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 276.26 | 10 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 276.85 | 3 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 278.7 | 7 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 278.99 | 7 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 324.93 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 336.93 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 338.46 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 347.63 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 365.13 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 384.28 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 393.61 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 434.12 | 2 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 436.93 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 442.74 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 579.02 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 606.17 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 627.1 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 1,182.28 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 794.32 | 12 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 426.42 | 3 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 409.7 | 8 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 426.42 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 83.61 | 1 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 397.16 | 9 | MUIRWOODS ECOCITY EXTENSION - 7 |
| PLOT | 274.35 | 7 | MUIRWOODS ECOCITY EXTENSION - 7 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-04-24 | |
|---|---|---|
| Proposed completion | 2029-04-23 |
Quarterly progress
| 2024-Q2 | 2024-07-12 |
| 2024-Q3 | 2024-10-07 |
| 2024-Q4 | 2025-01-13 |
| 2025-Q1 | 2025-04-13 |
| 2025-Q2 | 2025-07-14 |
| 2025-Q3 | 2025-10-14 |
| 2025-Q4 | 2026-01-12 |
| 2026-Q1 | 2026-04-12 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | THE GREATER PUNJAB OFFICERS CO-OP HOUSE BUILDING SOCIETY LTD | |
|---|---|---|
| Type | Other | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11961&inPromoter_ID=2846&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2024-04-16
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2022-12-27
- Commencement Certificate (Mega Project Category) · Sign in to download
- Environment Clearance certificate/ NOC · 2023-12-28
- License as Promoter from competent Authority · 2020-12-02
- Other Document (Approved CLU) · 2022-03-07
- Other Document (Drainage Receipt) · 2023-11-28 · Sign in to download
- Other Document (Drainage) · 2023-11-20 · Sign in to download
- Other Document (GMADA DEHYPOTHECATION LETTER) · 2024-04-12 · Sign in to download
- Other Document (NOC AIR) · 2023-09-18
- Other Document (NOC FOREST) · 2023-09-15
- Other Document (NOC PSPCL) · 2023-12-27
- Other Document (PAPRA EXEMPTION) · 2024-04-15 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2023-12-28
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Environment Clearance certificate/ NOC · 2023-12-28
- License as Promoter from competent Authority · 2020-12-02
- Other Document (Approved CLU) · 2022-03-07
- Other Document (NOC AIR) · 2023-09-18
- Other Document (NOC FOREST) · 2023-09-15
- Other Document (NOC PSPCL) · 2023-12-27
- Pollution Clearance from Punjab Pollution Control Board · 2023-12-28
- 2024-Q2 · 2024-07-12
- 2024-Q3 · 2024-10-07
- 2024-Q4 · 2025-01-13
- 2025-Q1 · 2025-04-13
- 2025-Q2 · 2025-07-14
- 2025-Q3 · 2025-10-14
- 2025-Q4 · 2026-01-12
- 2026-Q1 · 2026-04-12
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-12