Overview
MURLI NIWAS
DURGA HOME CONSTRUCTION · Patna
Booked6As of 2026-06-30
Construction progress69%As of 2026-06-30
Completion2027-12-31Proposed
Registered on2023-09-18
Valid to2027-12-31
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details |
| Construction & progress | 4 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 13 source links |
Registration
Registration
| Promoter | DURGA HOME CONSTRUCTION | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP65704-003/97/R-1604/2023 | |
| Registered on | 2023-09-18 | |
| Valid to | 2027-12-31 | |
| Project type | Residential | |
| Status (as filed) | RERA Registered Projects | |
| Proposed completion | 2027-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance | 9999-12-31 | |
| Fire NOC | 9999-12-31 | OFFICE OF THE STATE FIRE OFFICER -CUM DIRECTOR BIHAR PATNA |
| Airport NOC | 9999-12-31 | AIRPORTS AUTHORITY OF INDIA |
| Water Supply Permission | 9999-12-31 | |
| Other approval | 9999-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 752.98 | |
|---|---|---|
| Built-up (m²) | 1,693.92 | |
| FAR | 2.31 | |
| Towers | 1 | |
| Booked | 6 | |
| Booked as of | 2026-06-30 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 69% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2023-10-31 | |
| Proposed completion | 2027-12-31 |
Quarterly progress
| 2026-Q2 | 2026-07-31 | 69% | 6 |
| 2026-Q1 | 2026-04-30 | ||
| 2025-Q4 | 2026-01-31 | ||
| 2025-Q3 | 2025-11-22 | ||
| 2025-Q2 | 2025-07-16 | ||
| 2025-Q1 | 2025-04-14 | ||
| 2024-Q4 | 2025-01-11 | ||
| 2024-Q3 | 2024-10-30 | ||
| 2024-Q2 | 2024-08-21 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DURGA HOME CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | BANK OF BARODA | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP06112019165704_003
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP06112019165704&ld=pan&pj=RERAP06112019165704_003&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP06112019165704_003
- https://rera.bihar.gov.in/RCpage.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Upload Sanctioned Layout Plan
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- CA certificate · Sign in to download
- Sanctioned Building Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-31
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-30
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-31
- Q2 (Jul - Sep) / 2025-2026 · 2025-11-22
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-16
- Q4-Jan to Mar / 2024-2025 · 2025-04-14
- Q3-Oct to Dec / 2024-2025 · 2025-01-11
- Q2-Jun to Sep / 2024-2025 · 2024-10-30
- Q1-Apr to Jun / 2024-2025 · 2024-08-21
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2026-Q1 · 2026-04-30
- 2025-Q4 · 2026-01-31
- 2025-Q3 · 2025-11-22
- 2025-Q2 · 2025-07-16
- 2025-Q1 · 2025-04-14
- 2024-Q4 · 2025-01-11
- 2024-Q3 · 2024-10-30
- 2024-Q2 · 2024-08-21