Overview
NAGESHWAR PALACE
MAGADH GREEN HOMES · Patna
Units56
Completion2023-05-31Proposed
Registered on2019-03-29
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 11 source links |
Registration
Registration
| Promoter | MAGADH GREEN HOMES | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00310-2/807/R-538/2019 | |
| Registered on | 2019-03-29 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2023-05-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,015.4 | |
|---|---|---|
| Built-up (m²) | 5,033.05 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 56 |
Unit types
| 1 BHK | 1 | NAGESHWAR PALACE |
| 2 BHK | 8 | NAGESHWAR PALACE |
| 3 BHK | 5 | NAGESHWAR PALACE |
| 2 BHK | 18 | NAGESHWAR PALACE |
| 3 BHK | 24 | NAGESHWAR PALACE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-01-16 | |
|---|---|---|
| Proposed completion | 2023-05-31 |
Quarterly progress
| 2020-Q3 | 2021-02-23 |
| 2020-Q2 | 2021-02-23 |
| 2020-Q1 | 2021-02-23 |
| 2019-Q4 | 2021-02-23 |
| 2019-Q3 | 2021-02-23 |
| 2019-Q2 | 2021-02-23 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAGADH GREEN HOMES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP12032018100310-2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP12032018100310-2
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2-Jul to Sep / 2020-2021 · 2021-02-23
- Q1-Apr to Jun / 2020-2021 · 2021-02-23
- Q4-Jan to Mar / 2019-2020 · 2021-02-23
- Q3-Oct to Dec / 2019-2020 · 2021-02-23
- Q2-Jul to Sep / 2019-2020 · 2021-02-23
- Q1-Apr to Jun / 2019-2020 · 2021-02-23
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2020-Q3 · 2021-02-23
- 2020-Q2 · 2021-02-23
- 2020-Q1 · 2021-02-23
- 2019-Q4 · 2021-02-23
- 2019-Q3 · 2021-02-23