Overview
Nakshatra Veda
Overview
Nakshatra Veda
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Developer's project loan | ₹18.5 L secured · ₹6.01 Cr unsecured |
|---|
Approvals
| Layout approval | 1 filed · latest filed 12 Aug 2026 |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2027 |
Disputes & cases
Builder: JSB HOMEMAKERS PVT LTD
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
6 other registrations under this promoter's exact name in Maharashtra; a complaint on one is listed when MahaRERA lists it.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Carpet area | Units filed | Sold | Unsold | Median ₹/sq ft carpet |
|---|---|---|---|---|
| 101–150 sq ft · 9.3–13.9 sq m | 10 | 7 | 3 | ₹10,906 |
| 161–223 sq ft · 14.9–20.7 sq m | 10 | 5 | 4 | ₹14,384 |
| 252–322 sq ft · 23.4–29.9 sq m | 157 | 155 |
Location & risks
| Nearest mapped waterway or drain | None mapped within 3 km | |
|---|---|---|
| Nearest mapped inland water body | None mapped within 3 km |
Construction & progress
Developer
Loan & collateral
| Developer's project loan | ₹18.5 L secured · ₹6.01 Cr unsecured |
|---|
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 26 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
All projects in Palghar → · All projects in Maharashtra → (12 of 1,290 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| Registration number | P99000047826 | |
|---|---|---|
| Registered | 28 Nov 2022 |
| ₹11,986 |
| 376–418 sq ft · 34.9–38.9 sq m | 72 | 71 | 1 | ₹10,774 |
| 484–537 sq ft · 45.0–49.9 sq m | 90 | 89 | 0 | ₹10,110 |
| 977 sq ft · 90.81 sq m | 1 | 0 | 0 | – |
| Building | Units filed | Sold | Median ₹/sq ft carpet |
|---|---|---|---|
| Wing H | 171 | 160 | ₹12,354 |
| Wing I | 169 | 167 | ₹11,254 |
| Carpet area | Unsold units | Carpet area, total |
|---|---|---|
| 101–150 sq ft · 9.3–13.9 sq m | 3 | 344 sq ft |
| 161–223 sq ft · 14.9–20.7 sq m | 4 | 716 sq ft |
| 252–322 sq ft · 23.4–29.9 sq m | 2 | 615 sq ft |
| 376–418 sq ft · 34.9–38.9 sq m | 1 | 412 sq ft |
| All unsold | 10 | 2,087 sq ft |
| Nearest mapped waterway or drain | None mapped within 3 km |
|---|
| Landfill or waste transfer station | None mapped within 3 km | |
|---|---|---|
| Sewage treatment plant | None mapped within 3 km | |
| Quarry | None mapped within 3 km | |
| Crematorium | None mapped within 3 km | |
| Prison | None mapped within 3 km | |
| Electrical substation | None mapped within 3 km |
| RERA completion date | 31 Dec 2027 | |
|---|---|---|
| Registered | 28 Nov 2022 |
| Engineer's certificate, Form 2 | 7 filed · latest filed 26 Jun 2026 | |
|---|---|---|
| Chartered accountant's certificate, Form 3 | 4 filed · latest filed 30 Aug 2025 |
Land · ₹23.92 Cr 25.2%Development · ₹71.14 Cr 74.8%
| Estimated cost, at registration | ₹95.06 Cr |
|---|
Sold 97%Unsold 3%
| Units filed | 340 | |
|---|---|---|
| Sold | 318 · 94% | |
| Unsold | 10 |
| Escrow balance | ₹0 (INR) | |
|---|---|---|
| Filed withdrawal amount | ₹93,91,10,319 (INR) |
| MahaRERA registrations under this promoter | 7 | |
|---|---|---|
| Marked completed | 0 | |
| Past promised date, not completed | 0 | |
| Other phases under this promoter name | 6 | |
| With a filed extension or completion | 5 (0 completed, 5 extended) | |
| Average schedule slip | 4 months |