Overview
NARENDRA VILLA
MAURYA VIHAR CONSTRUCTIONS PRIVATE LIMITED · Patna
Units36
Completion2025-08-10Proposed
Registered on2021-08-17
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 3 unit types |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 20 source links |
Registration
Registration
| Promoter | MAURYA VIHAR CONSTRUCTIONS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP12102-1/1349/R-1182/2021 | |
| Registered on | 2021-08-17 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2025-08-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,102.62 | |
|---|---|---|
| Built-up (m²) | 2,755.95 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 36 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 12 | NARENDRA VILLA |
| Shop | 12 | NARENDRA VILLA |
| 2 BHK | 12 | NARENDRA VILLA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-03-01 | |
|---|---|---|
| Proposed completion | 2025-08-10 |
Quarterly progress
| 2024-Q4 | 2025-01-08 |
| 2024-Q3 | 2024-10-06 |
| 2024-Q2 | 2024-07-15 |
| 2024-Q1 | 2024-07-25 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-09 |
| 2022-Q4 | 2023-04-09 |
| 2022-Q3 | 2023-04-09 |
| 2022-Q2 | 2022-07-09 |
| 2022-Q1 | 2022-04-14 |
| 2021-Q4 | 2022-01-13 |
| 2021-Q3 | 2021-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAURYA VIHAR CONSTRUCTIONS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP12202020112102-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP12202020112102-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Q3-Oct to Dec / 2024-2025 · 2025-01-08
- Q2-Jul to Sep / 2024-2025 · 2024-10-06
- Q1-Apr to Jun / 2024-2025 · 2024-07-15
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-09
- Q3-Oct to Dec / 2022-2023 · 2023-04-09
- Q2-Jul to Sep / 2022-2023 · 2023-04-09
- Q1-Apr to Jun / 2022-2023 · 2022-07-09
- Q4-Jan to Mar / 2021-2022 · 2022-04-14
- Q3-Oct to Dec / 2021-2022 · 2022-01-13
- Q2-Jul to Sep / 2021-2022 · 2021-10-12
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2024-Q4 · 2025-01-08
- 2024-Q3 · 2024-10-06
- 2024-Q2 · 2024-07-15
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-09
- 2022-Q4 · 2023-04-09
- 2022-Q3 · 2023-04-09
- 2022-Q2 · 2022-07-09
- 2022-Q1 · 2022-04-14
- 2021-Q4 · 2022-01-13
- 2021-Q3 · 2021-10-12