Title & ownership
Approvals
| Building plan (BDA) | Sanctioned 25 Nov 2022 · No. 1978/2022-2023 | |
|---|---|---|
| Power NOC | Filed with the registration | |
| Fire department |
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Land · ₹7.69 Cr 59.8%Development · ₹5.18 Cr
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Building plan (BDA) | Sanctioned 25 Nov 2022 | |
| Escrow bank | HDFC · Vijaynagar, Bangalore |
Data room
181 documents filed with K-RERA for this project
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. The drawn plot is a whole survey number, not the project's own share of it; it shows where the land is, not the site.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | 1 | – | – | Red flag |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| Aaradhya GardensRegistered · no quarterly update yet | SAI SAMRUDHI CONSTRUCTIONS | Apartment | 992 sqft carpet (as filed) | Dec 2028 |
| Aashirvad Siddhi PriyaFiled as completed · no completion certificate on record | SEENAPPA P | Plot | ~600–1,240 sqft (estimate: filed carpet plus 25%) | Nov 2024 |
| Aashirvad's Panchamukhi ShreyodhamaCompleted (regulator flag) | RAJESHWARI AASHIRVAD INFRA PROJECTS PRIVATE LIMITED | Plot | ~1,650 sqft (estimate: filed carpet plus 25%) | Completed |
| Aditya OrchardLapsed · completion date passed | Mangala Raghavan | Plot | ~1,200–1,800 sqft (estimate: filed carpet plus 25%) | May 2024 |
| Aprameya Brindavanam EliteCompleted (regulator flag) | Aprameya Properties Pvt Ltd | Plot | – | Completed |
| Ashwasurya Atharva RitewayCompleted (regulator flag) | RITEWAY & KUBERA PROMOTERS | Plot | ~1,200–2,400 sqft (estimate: filed carpet plus 25%) | Completed |
| Axis Banyan CountyCompleted (regulator flag) | R.Harish babu | Plot | – | Completed |
| Birla Apple SpireLapsed · completion date passed | Apple spire India LLP | Apartment | 1,667 sqft carpet (as filed) | Sep 2019 |
8 of 121 other projects in Mysore Road, A to Z. Status is taken from each project's own filing.
All 126 projects in Mysore Road → · Vaishnodevi Lush Greens Private Limited's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Nature View in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Filed with the registration |
| SEIAA | Filed with the registration |
|---|
| AAI | Filed with the registration |
|---|
| KSPCB | Filed with the registration |
|---|
| Water supply NOC | Filed with the registration |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Jun 2024 |
| Land conversion | 3 of 3 parcels converted | |
|---|---|---|
| Sy 52/1 | Converted 20 Oct 2014 · DC Conversion | |
| Sy 52/2 | Converted 22 Feb 2018 · DC Conversion | |
| Sy 52/3 | Converted 19 Dec 2018 · DC Conversion | |
| Survey numbers | 52/1 · 52/2 · 52/3 |
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Projects within 4 km, counted | 11 (11 with an approximate location) | |
|---|---|---|
| Plots in them | 2,611 | |
| Booked | 1,558 of 2,611 (60%) | |
| Unsold | 1,053 | |
| Booked a month, pooled | 30 plots | |
| Months to sell, pooled | 34 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Residential (main), over the filed survey numbers | |
|---|---|---|
| Nearest government-flagged flood location | about 6 km, Kengeri Yellamma temple | |
| Government land in the filed surveys | Not found |
| Nearest storm drain | about 2 km to the south, Vrishabhavati, primary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank |
| Possession, agreement | 30 Jul 2023 | |
|---|---|---|
| RERA completion date | 30 Jun 2024 | Red flag |
| Work began, as filed | 2 Jan 2023 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Architect's certificate, registration | Dated 5 Jan 2023 · site inspected 4 Jan 2023 | |
|---|---|---|
| Engineer's certificate, registration | Dated 3 May 2023 | |
| Chartered accountant's certificate, registration | Dated 5 Jan 2023 |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost, at registration | ₹12.87 Cr | |
|---|---|---|
| Estimated cost, architect's certificate | ₹4.12 Cr | |
| Estimated cost, engineer's certificate | ₹2.50 Cr |
| Escrow bank | HDFC · Vijaynagar, Bangalore | |
|---|---|---|
| Share of collections the promoter declared for escrow | 70% |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 23.2 m
Taluk average; not a reading at the site.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 10 CGWB wells in Bengaluru South taluk read in this class | |
| Through the year | January 2025: 2.2 m (5 wells), Pre-monsoon 2025: 1.9 m (10 wells), August 2025: 1.5 m (11 wells), depth below ground of CGWB's monitoring wells in Bengaluru South taluk (the median where there are several) | |
| Water supply, as filed | Local authority (Panchayath) |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 2 km to the south, Vrishabhavati, primary drain | |
|---|---|---|
| Metro, operational | about 4.5 km, Challaghatta | |
| Metro, under construction | about 17.5 km, Kalena Agrahara |
| Kempegowda Airport | 57 | 47 |
| MG Road (CBD) | 24 | 21.5 |
| Manyata Tech Park | 34.5 | 28 |
| ITPL, Whitefield | 41.5 | 35 |
| Ecospace, Bellandur ORR | 38 | 27.5 |
| Electronic City Ph 1 | 35 | 26.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 2.5 km to the north-east, named STP-6 on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 1 km, named Kumbalagodu on OpenStreetMap |