Overview
NAYANTARA DREAMS
NAYAN TARA DEVELOPERS · DURG
Units84
Booked48 of 84As of 2025-12-31
Construction progress97%As of 2025-12-31
Completion2026-07-03Revised · Proposed 2025-03-03
Registered on2022-07-01
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 2 cost heads · 14 quarters |
| Technical report | |
| Site & area | 3 site details · 84 unit types |
| Construction & progress | 4 progress details · 14 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 91 documents · 9 source links |
Registration
Registration
| Promoter | NAYAN TARA DEVELOPERS | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA010722001461 | |
| Registered on | 2022-07-01 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2025-03-03 | |
| Revised completion | 2026-07-03 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Enviornment Clearance |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,00,00,000 | |
|---|---|---|
| Construction | ₹8,35,29,000 |
Quarterly money flows
| 2022-Q3 | ₹0 |
| 2022-Q4 | ₹46,37,923 |
| 2023-Q1 | ₹67,77,937 |
| 2023-Q2 | ₹34,95,102 |
| 2023-Q3 | ₹2 |
| 2023-Q4 | ₹2 |
| 2024-Q1 | ₹241 |
| 2024-Q2 | ₹52,27,141 |
| 2024-Q3 | ₹2 |
| 2024-Q4 | ₹36,85,152 |
| 2025-Q1 | ₹39,27,002 |
| 2025-Q2 | ₹66,97,714 |
| 2025-Q3 | ₹1,40,002 |
| 2025-Q4 | ₹1,56,602 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 84 | |
|---|---|---|
| Booked | 48 | |
| Booked as of | 2025-12-31 |
Unit types
| block a-a1 | 1 | 0 |
| BLOCK A-A2 | 1 | 0 |
| BLOCK A-A3 | 1 | 0 |
| BLOCK A-A4 | 1 | 0 |
| BLOCK A-A5 | 1 | 0 |
| BLOCK A-A7 | 1 | 1 |
| BLOCK A-A8 | 1 | 0 |
| BLOCK A-A13 | 1 | 1 |
| BLOCK A-A14 | 1 | 0 |
| BLOCK B-B1 | 1 | 1 |
| BLOCK B-B2 | 1 | 1 |
| BLOCK B-B3 | 1 | 1 |
| BLOCK B-B4 | 1 | 1 |
| BLOCK B-B5 | 1 | 1 |
| BLOCK B-B6 | 1 | 1 |
| BLOCK B-B7 | 1 | 1 |
| BLOCK B-B8 | 1 | 1 |
| BLOCK B-B9 | 1 | 1 |
| BLOCK B-B10 | 1 | 1 |
| BLOCK B-B11 | 1 | 1 |
| BLOCK B-B12 | 1 | 0 |
| BLOCK B-B13 | 1 | 0 |
| BLOCK B-B14 | 1 | 0 |
| BLOCK B-B15 | 1 | 1 |
| BLOCK B-B16 | 1 | 1 |
| BLOCK B-B17 | 1 | 1 |
| BLOCK B-B18 | 1 | 1 |
| BLOCK B-B19 | 1 | 1 |
| BLOCK B-B20 | 1 | 1 |
| BLOCK B-B21 | 1 | 1 |
| BLOCK B-B22 | 1 | 0 |
| BLOCK B-B23 | 1 | 0 |
| BLOCK B-B24 | 1 | 1 |
| BLOCK B-B25 | 1 | 0 |
| BLOCK B-B26 | 1 | 1 |
| BLOCK B-B27 | 1 | 0 |
| BLOCK B-B28 | 1 | 0 |
| BLOCK B-B29 | 1 | 1 |
| BLOCK B-B30 | 1 | 1 |
| BLOCK B-B31 | 1 | 1 |
| BLOCK B-B32 | 1 | 1 |
| BLOCK B-B33 | 1 | 0 |
| BLOCK B-B34 | 1 | 0 |
| BLOCK B-B35 | 1 | 0 |
| BLOCK B-B36 | 1 | 1 |
| BLOCK B-B37 | 1 | 1 |
| BLOCK B-B38 | 1 | 1 |
| BLOCK B-B39 | 1 | 1 |
| BLOCK B-B40 | 1 | 1 |
| BLOCK B-B41 | 1 | 1 |
| BLOCK B-B42 | 1 | 1 |
| BLOCK B-B43 | 1 | 1 |
| BLOCK B-B44 | 1 | 1 |
| BLOCK B-B45 | 1 | 1 |
| BLOCK B-B46 | 1 | 1 |
| BLOCK B-B47 | 1 | 1 |
| BLOCK B-B48 | 1 | 1 |
| BLOCK B-B49 | 1 | 1 |
| block b-b50 | 1 | 1 |
| block b-b51 | 1 | 1 |
| block b-B52 | 1 | 1 |
| block b-B53 | 1 | 1 |
| BLOCK C-C1 | 1 | 0 |
| block C-C2 | 1 | 0 |
| block C-C3 | 1 | 1 |
| block C-C4 | 1 | 1 |
| block C-C5 | 1 | 0 |
| LIG-L1 | 1 | 1 |
| LIG-L2 | 1 | 1 |
| LIG-L3 | 1 | 0 |
| LIG-L4 | 1 | 0 |
| LIG-L5 | 1 | 0 |
| LIG-L6 | 1 | 0 |
| LIG-L7 | 1 | 0 |
| LIG-L8 | 1 | 0 |
| LIG-L9 | 1 | 0 |
| LIG-L10 | 1 | 0 |
| LIG-L11 | 1 | 0 |
| LIG-L12 | 1 | 0 |
| BLOCK A-A6 | 1 | 0 |
| BLOCK A-A9 | 1 | 0 |
| BLOCK A-A10 | 1 | 0 |
| BLOCK A-A11 | 1 | 0 |
| BLOCK A-A12 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 97% | |
|---|---|---|
| As of | 2025-12-31 | |
| Proposed completion | 2025-03-03 | |
| Revised completion | 2026-07-03 |
Quarterly progress
| 2022-Q3 | 18% |
| 2022-Q4 | 20% |
| 2023-Q1 | 30% |
| 2023-Q2 | 35% |
| 2023-Q3 | 39% |
| 2023-Q4 | 48% |
| 2024-Q1 | 54% |
| 2024-Q2 | 63% |
| 2024-Q3 | 72% |
| 2024-Q4 | 75% |
| 2025-Q1 | 85% |
| 2025-Q2 | 89% |
| 2025-Q3 | 97% |
| 2025-Q4 | 97% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NAYAN TARA DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTc1NQ==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Document
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Development Permission from competent authorities