Overview
NEELKANTHA DINESH RESIDENCY
NEELKANTHA SOLUTIONS PVT LTD · Patna
Units30
Completion2019-03-31Proposed
Registered on2018-09-27
Approvals2
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 2 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 5 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 34 documents · 15 source links |
Registration
Registration
| Promoter | NEELKANTHA SOLUTIONS PVT LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00283-1/229/R-195/2018 | |
| Registered on | 2018-09-27 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2019-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status |
|---|---|---|---|
| RERA/CC/84/2022 | RERA Bihar | Complaint | Pending |
| NEELKANTHA DINESH RESIDENCY | RERA Bihar | Pending |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹58,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,136.52 | |
|---|---|---|
| Built-up (m²) | 2,492.95 | |
| FAR | 2.13 | |
| Towers | 1 | |
| Units | 30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 10 | NEELKANTHA DINESH RESIDENCY |
| 3 BHK | 20 | NEELKANTHA DINESH RESIDENCY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2013-10-01 | |
|---|---|---|
| Proposed completion | 2019-03-31 |
Quarterly progress
| 2019-Q3 | 2022-08-11 |
| 2019-Q2 | 2022-08-11 |
| 2019-Q1 | 2022-08-11 |
| 2018-Q4 | 2022-08-11 |
| 2018-Q3 | 2022-08-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NEELKANTHA SOLUTIONS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | Corporation Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP244201800283-1
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP244201800283-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2-Jul to Sep / 2019-2020 · 2022-08-11
- Q1-Apr to Jun / 2019-2020 · 2022-08-11
- Q4-Jan to Mar / 2018-2019 · 2022-08-11
- Q3-Oct to Dec / 2018-2019 · 2022-08-11
- Q2-Jul to Sep / 2018-2019 · 2022-08-11
- Case proceeding RERA/CC/84/2022 · 2023-03-14 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2023-08-01 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2023-10-06 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2023-10-09 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2023-12-07 · Sign in to download
- Case proceeding NEELKANTHA DINESH RESIDENCY · 2024-02-01 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2024-02-01 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2024-03-06 · Sign in to download
- Case proceeding RERA/CC/84/2022 · 2024-04-25 · Sign in to download
- Other · 2024-06-21 · Sign in to download
- Other · 2024-05-31 · Sign in to download
- Other · 2024-07-01 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- RERA/CC/84/2022 · Sign in to download
- NEELKANTHA DINESH RESIDENCY · Sign in to download
- 2019-Q3 · 2022-08-11
- 2019-Q2 · 2022-08-11
- 2019-Q1 · 2022-08-11
- 2018-Q4 · 2022-08-11
- 2018-Q3 · 2022-08-11