| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Developer's project loan | ₹69.02 Cr secured · ₹1.00 Cr unsecured |
|---|
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Apr 2027 |
| Registration number | P51800050433 | |
|---|---|---|
| Registered | 12 Apr 2023 |
Disputes & cases
Builder: NEELKAMAL REALTY & CONSTRUCTION LLP
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
This is the only registration under this promoter's exact name in Maharashtra.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Carpet area | Units filed | Sold | Unsold | Median ₹/sq ft carpet |
|---|---|---|---|---|
| 188–290 sq ft · 17.5–26.9 sq m | 14 | 10 | 4 | ₹26,617 |
| 347–419 sq ft · 32.3–38.9 sq m | 5 |
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | ₹69.02 Cr secured · ₹1.00 Cr unsecured |
|---|
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 33 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Mapped waterways, water bodies, roads and transport stations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
All projects in Mumbai Suburban → · All projects in Mumbai → (12 of 2,942 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| 1 |
| ₹26,532 |
| 606–673 sq ft · 56.3–62.5 sq m | 3 | 0 | 3 | – |
| 772–860 sq ft · 71.7–79.9 sq m | 165 | 55 | 110 | ₹24,685 |
| 1,002–1,004 sq ft · 93.1–93.3 sq m | 23 | 4 | 19 | ₹23,766 |
| 1,129–1,229 sq ft · 104.9–114.2 sq m | 42 | 25 | 17 | ₹25,464 |
| 1,633–1,675 sq ft · 151.7–155.6 sq m | 23 | 2 | 21 | – |
| Building | Units filed | Sold | Median ₹/sq ft carpet |
|---|---|---|---|
| SALE WING A | 91 | 37 | ₹25,714 |
| SALE WING B | 88 | 25 | ₹25,001 |
| SALE WING C | 91 | 38 | ₹24,892 |
| REHAB BUILDING | 5 | 0 | – |
| Carpet area | Unsold units | Carpet area, total |
|---|---|---|
| 188–290 sq ft · 17.5–26.9 sq m | 4 | 810 sq ft |
| 347–419 sq ft · 32.3–38.9 sq m | 1 | 347 sq ft |
| 606–673 sq ft · 56.3–62.5 sq m | 3 | 1,943 sq ft |
| 772–860 sq ft · 71.7–79.9 sq m | 110 | 87,764 sq ft |
| 1,002–1,004 sq ft · 93.1–93.3 sq m | 19 | 19,035 sq ft |
| 1,129–1,229 sq ft · 104.9–114.2 sq m | 17 | 20,202 sq ft |
| 1,633–1,675 sq ft · 151.7–155.6 sq m | 21 | 35,091 sq ft |
| All unsold | 175 | 1,65,193 sq ft |
| Projects within 4 km, counted | 111 (111 with an approximate location) | |
|---|---|---|
| Flats in them | 15,327 | |
| Sold or booked | 10,664 of 15,327 (70%) | |
| Unsold | 4,663 |
Map of mapped waterways within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
| Nearest mapped waterway or drain | about 0.5 km, Aarey, drain | |
|---|---|---|
| Nearest mapped inland water body | about 0.5 km, an unnamed pond |
| RERA completion date | 30 Apr 2027 | |
|---|---|---|
| Registered | 12 Apr 2023 | |
| Completion date first filed | 31 Dec 2026 |
| Architect's certificate, Form 1 | 6 filed · latest filed 28 Jul 2026 | |
|---|---|---|
| Chartered accountant's certificate, Form 3 | 3 filed · latest filed 28 Jul 2026 |
Land · ₹148.04 Cr 35.8%Development · ₹266.00 Cr 64.2%
| Estimated cost, at registration | ₹414.04 Cr |
|---|
Sold 36.4%Unsold 63.6%
| Units filed | 275 | |
|---|---|---|
| Sold | 100 · 36% | |
| Unsold | 175 |
| Escrow balance | ₹1,51,72,557 (INR) | |
|---|---|---|
| Filed withdrawal amount | ₹1,23,83,80,077 (INR) |
Map of mapped waterways and water bodies within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
Well within 3 km of filed pin; not a site reading.
| Groundwater | monitoring well, 2026-01-10: 0.1 m below ground |
|---|
Mapped waterways, water bodies, roads and transport stations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
| Nearest mapped waterway or drain | about 0.5 km, Aarey, drain |
|---|
| Chhatrapati Shivaji Maharaj International Airport | 5.5 |
| Nariman Point | 24 |
| Chhatrapati Shivaji Terminus | 22.5 |
| Bandra Kurla Complex | 9 |
| Powai | 4.5 |
| Landfill or waste transfer station | None mapped within 3 km | |
|---|---|---|
| Sewage treatment plant | None mapped within 3 km | |
| Quarry | None mapped within 3 km | |
| Crematorium | None mapped within 3 km | |
| Prison | None mapped within 3 km | |
| Electrical substation | about 1 km |