Overview
NIL RAJ
HORIZON HEIGHT CONSTRUCTION · Patna
Units12
Completion2024-12-10Proposed
Registered on2021-07-28
Approvals2
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 22 source links |
Registration
Registration
| Promoter | HORIZON HEIGHT CONSTRUCTION | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP94443-1/1320/R-1173/2021 | |
| Registered on | 2021-07-28 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2024-12-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind |
|---|---|---|
| RERA/CC/100/2022 | RERA Bihar | Complaint |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,75,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 506.11 | |
|---|---|---|
| Built-up (m²) | 917.21 | |
| FAR | 1.89 | |
| Towers | 1 | |
| Units | 12 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 6 | NIL RAJ |
| 3 BHK | 6 | NIL RAJ |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-11-26 | |
|---|---|---|
| Proposed completion | 2024-12-10 |
Quarterly progress
| 2025-Q1 | 2025-06-09 |
| 2024-Q4 | 2025-06-09 |
| 2024-Q3 | 2024-11-23 |
| 2024-Q2 | 2024-11-23 |
| 2024-Q1 | 2024-11-23 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2024-07-25 |
| 2022-Q4 | 2023-01-27 |
| 2022-Q3 | 2022-10-17 |
| 2022-Q2 | 2025-06-09 |
| 2022-Q1 | 2022-04-18 |
| 2021-Q4 | 2022-01-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HORIZON HEIGHT CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Allahabad Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP11012020094443-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP11012020094443-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Q4-Jan to Mar / 2024-2025 · 2025-06-09
- Q3-Oct to Dec / 2024-2025 · 2025-06-09
- Q2-Jun to Sep / 2024-2025 · 2024-11-23
- Q1-Apr to Jun / 2024-2025 · 2024-11-23
- Q4-Jan to Mar / 2023-2024 · 2024-11-23
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2023-01-27
- Q2-Jul to Sep / 2022-2023 · 2022-10-17
- Q1-Apr to Jun / 2022-2023 · 2025-06-09
- Q4-Jan to Mar / 2021-2022 · 2022-04-18
- Q3-Oct to Dec / 2021-2022 · 2022-01-15
- Case proceeding RERA/CC/100/2022 · 2022-12-22 · Sign in to download
- Other · 2022-12-22 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- RERA/CC/100/2022 · Sign in to download
- 2025-Q1 · 2025-06-09
- 2024-Q4 · 2025-06-09
- 2024-Q3 · 2024-11-23
- 2024-Q2 · 2024-11-23
- 2024-Q1 · 2024-11-23
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2023-01-27
- 2022-Q3 · 2022-10-17
- 2022-Q2 · 2025-06-09
- 2022-Q1 · 2022-04-18
- 2021-Q4 · 2022-01-15