Overview
NIRMALA DHAWA PARADISE
NIRMALA INFRADEVELOPERS LIMITED · Lucknow
Units120
Completion2021-03-28Revised · Proposed 2019-09-30
Registered on2017-11-13
Valid to2021-03-28
Approvals6
Complaints3As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 3 project complaints · 39 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 15 unit types |
| Construction & progress | 3 progress details · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 7 documents · 7 source links |
Registration
Registration
| Promoter | NIRMALA INFRADEVELOPERS LIMITED | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ14368 | |
| Registered on | 2017-11-13 | |
| Valid to | 2021-03-28 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2019-09-30 | |
| Revised completion | 2021-03-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Original permit | 101 | 2017-08-17 | 2022-08-16 | Lucknow Development Authority |
| Original permit | 101 | 2017-08-17 | 2022-08-16 | Lucknow Development Authority |
| Original permit | 101 | 2017-08-17 | 2019-08-16 | Lucknow Development Authority |
| Revalidated permit | 101 | 2017-08-17 | 2021-09-22 | Lucknow Development Authority |
| Original permit | 101 | 2017-08-17 | 2019-08-16 | Lucknow Development Authority |
| Revalidated permit | 101 | 2017-08-17 | 2021-09-22 | Lucknow Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 3 | |
|---|---|---|
| Promoter | 39 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹7,42,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,350 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 4 | |
| Units | 120 |
Unit types
| 2 BHK | 57.97 | 8 | Q | GF |
| 2 BHK | 57.97 | 8 | Q | 1 |
| 2 BHK | 57.97 | 8 | Q | 2 |
| 2 BHK | 57.97 | 8 | Q | 3 |
| 2 BHK | 57.97 | 8 | Q | 4 |
| 1 BHK | 38.65 | 8 | A | GF |
| 1 BHK | 38.65 | 8 | A | 1 |
| 1 BHK | 38.65 | 8 | A | 2 |
| 1 BHK | 38.65 | 8 | A | 3 |
| 1 BHK | 38.65 | 8 | A | 4 |
| 1 BHK | 38.65 | 8 | H | GF |
| 1 BHK | 38.65 | 8 | H | 1 |
| 1 BHK | 38.65 | 8 | H | 2 |
| 1 BHK | 38.65 | 8 | H | 3 |
| 1 BHK | 38.65 | 8 | H | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-04-20 | |
|---|---|---|
| Proposed completion | 2019-09-30 | |
| Revised completion | 2021-03-28 |
Extensions
| Valid to | Reason |
|---|---|
| 2020-09-29 | |
| 2021-03-28 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NIRMALA INFRADEVELOPERS LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | CORPORATION BANK | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=IU/IrEfg0GY=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=6U+TuzztprYaQchWgl9IEdn8buackbjn&PaURJEMAN4=ZL9MNERkNdapnvJFmw6/VA==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=IU/IrEfg0GY=
- Document
- Other Plan(If Any) · 2019-07-31
- Waste Disposal Plan · 2019-08-28
- Water Supply Plan · 2019-08-28
- Development Work Plan · 2019-07-31
- CA CERTIFICATE · 2019-09-11 · Sign in to download
- ENGINEERS CERTIFICATE · 2019-09-25 · Sign in to download