Overview
Noor Shopping Centre
Grid Builders and Developers · Jalandhar
Units56
Completion2030-10-31Proposed
Valid to2030-10-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 14 source links |
Registration
Registration
| Promoter | Grid Builders and Developers | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL36-PC0441 | |
| Valid to | 2030-10-31 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2030-10-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | 2026-04-30 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from NHAI/ PWD | 2025-11-03 | |
| Other Document (Affidavit NOC) | Legal Documents (Received) | 2026-05-02 |
| Other Document (Drainage NOC) | 2025-09-29 | |
| Other Document (Forest NOC) | 2025-12-19 | |
| Pollution Clearance from Punjab Pollution Control Board | 2026-06-05 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹12,71,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,214.02 | |
|---|---|---|
| Units | 56 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Plot No. 1-2, 4-5 | 64.705 | 4 | COMMERCIAL PLOTS FOR SHOPS |
| Plot No. 3 and 6 | 104.752 | 2 | COMMERCIAL PLOTS FOR SHOPS |
| Plot No. 7-16, 18-56 | 51.026 | 50 | COMMERCIAL PLOTS FOR SHOPS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-03-10 | |
|---|---|---|
| Proposed completion | 2030-10-31 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q3 | 2026-10-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Grid Builders and Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12744&inPromoter_ID=3565&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2026-04-30
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2025-11-03
- Other Document (Drainage NOC) · 2025-09-29
- Other Document (Forest NOC) · 2025-12-19
- Pollution Clearance from Punjab Pollution Control Board · 2026-06-05
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2026-04-30
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2025-11-03
- Other Document (Affidavit NOC) · 2026-05-02
- Other Document (Drainage NOC) · 2025-09-29
- Other Document (Forest NOC) · 2025-12-19
- Pollution Clearance from Punjab Pollution Control Board · 2026-06-05
- 2026-Q3 · 2026-10-14