Overview
North Avenue
GRS INFRA HOUSING · Sahibzada Ajit Singh Nagar (Mohali)
Units85
Completion2030-03-19Proposed
Valid to2030-03-19
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 45 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 19 source links |
Registration
Registration
| Promoter | GRS INFRA HOUSING | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR1178 | |
| Valid to | 2030-03-19 | |
| Project type | (1) Residential (Building/Tower Development) (2) Residential (Building/Tower Development) (3) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2030-03-19 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Permissions (Received) | 2024-05-27 |
| CLU Certificate | ||
| Electric Substation NOC | 2025-03-31 | |
| Environment Clearance certificate/ NOC | Legal Documents (Received) | 2025-05-20 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2024-03-09 |
| NOC from Mining Department | Permissions (Received) | 2023-11-17 |
| Other Document (FOREST NOC ) | Permissions (Received) | 2024-01-16 |
| Other Document (UNDERTAKING REGARDING REMAINING NOC ) | Legal Documents (Received) | 2025-04-18 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-04-18 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹43,75,89,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,161.58 | |
|---|---|---|
| Towers | 4 | |
| Maximum floors | 15 | |
| Units | 85 |
Unit types
| 1st Floor Flat no. 101-102 | 79.655 | 2 | TOWER A |
| 2nd Floor Flat no. 201-202 | 79.655 | 2 | TOWER A |
| 3rd Floor Flat no. 301-302 | 79.655 | 2 | TOWER A |
| 4th Floor Flat no. 401-402 | 79.655 | 2 | TOWER A |
| 5th Floor Flat no. 501-502 | 79.655 | 2 | TOWER A |
| 6th Floor Flat no. 601-602 | 79.655 | 2 | TOWER A |
| 7th Floor Flat no. 701-702 | 79.655 | 2 | TOWER A |
| 8th Floor Flat no. 801-802 | 79.655 | 2 | TOWER A |
| 9th Floor Flat no. 901-902 | 79.655 | 2 | TOWER A |
| 10th Floor Flat no. 1002 | 73.561 | 1 | TOWER A |
| 11th Floor Flat no. 1102 | 73.561 | 1 | TOWER A |
| 13th and 14th Floor Flat no. 1301 | 83.807 | 1 | TOWER A |
| 12th Floor Flat no. 1201 | 87.749 | 1 | TOWER A |
| 1st Floor Flat no. 101-102 | 79.655 | 2 | TOWER B |
| 2nd Floor Flat no. 201-202 | 79.655 | 2 | TOWER B |
| 3rd Floor Flat no. 301-302 | 79.655 | 2 | TOWER B |
| 4th Floor Flat no. 401-402 | 79.655 | 2 | TOWER B |
| 5th Floor Flat no. 501-502 | 79.655 | 2 | TOWER B |
| 6th Floor Flat no. 601-602 | 79.655 | 2 | TOWER B |
| 7th Floor Flat no. 701-702 | 79.655 | 2 | TOWER B |
| 8th Floor Flat no. 801-802 | 79.655 | 2 | TOWER B |
| 9th Floor Flat no. 901-902 | 79.655 | 2 | TOWER B |
| 10th Floor Flat no. 1001 and 1002 | 73.561 | 2 | TOWER B |
| 11th Floor Flat no. 1101 and 1102 | 73.561 | 2 | TOWER B |
| 13th and 14th Floor Flat no. 1302 | 83.807 | 1 | TOWER B |
| 12 Floor Flat no.1202 | 87.794 | 1 | TOWER B |
| 1st Floor Flat no. 101-102 | 79.655 | 2 | TOWER C |
| 2nd Floor Flat no. 201-202 | 79.655 | 2 | TOWER C |
| 3rd Floor Flat no. 301-302 | 79.655 | 2 | TOWER C |
| 4th Floor Flat no. 401-402 | 79.655 | 2 | TOWER C |
| 5th Floor Flat no. 501-502 | 79.655 | 2 | TOWER C |
| 6th Floor Flat no. 601-602 | 79.655 | 2 | TOWER C |
| 7th Floor Flat no. 701-702 | 79.655 | 2 | TOWER C |
| 8th Floor Flat no. 801-802 | 79.655 | 2 | TOWER C |
| 9th Floor Flat no. 901-902 | 79.655 | 2 | TOWER C |
| 10th Floor Flat no. 1001 and 1002 | 73.561 | 2 | TOWER C |
| 11th Floor Flat no. 1101 and 1102 | 73.561 | 2 | TOWER C |
| 13th and 14th Floor Flat no. 1303 | 83.807 | 1 | TOWER C |
| 12 Floor Flat no.1203 | 87.794 | 1 | TOWER C |
| Stilt Floor Flat no. 1 (EWS) | 31.794 | 0 | TOWER D |
| Stilt Floor Flat no. 2 (EWS) | 37.871 | 1 | TOWER D |
| Ist Floor Flat no.101, 2nd Floor Flat no.201, 3rd Floor Flat no. 301 (EWS) | 31.794 | 3 | TOWER D |
| Ist Floor Flat no.102, 2nd Floor Flat no.202, 3rd Floor Flat no. 302 (EWS) | 44.984 | 3 | TOWER D |
| 4th Floor to 9th Floor Flat no. 401, 501, 601, 701, 801 and 901 | 79.655 | 6 | TOWER D |
| 10th Floor Flat no. 1001 and 11th Floor Flat no.1101 | 73.561 | 2 | TOWER D |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-03-20 | |
|---|---|---|
| Proposed completion | 2030-03-19 |
Quarterly progress
| 2025-Q2 | 2025-12-03 |
| 2025-Q3 | 2025-12-03 |
| 2025-Q4 | 2026-01-15 |
| 2026-Q1 | 2026-05-06 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GRS INFRA HOUSING | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12302&inPromoter_ID=3210&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-05-27
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-03-31
- Environment Clearance certificate/ NOC · 2025-05-20
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-03-09
- NOC from Mining Department · 2023-11-17
- Other Document (Access to Road) · 2025-05-09 · Sign in to download
- Other Document (FOREST NOC ) · 2024-01-16
- Other Document (UNDERTAKING REGARDING REMAINING NOC ) · 2025-04-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-18
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-05-27
- CLU Certificate
- Electric Substation NOC · 2025-03-31
- Environment Clearance certificate/ NOC · 2025-05-20
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-03-09
- NOC from Mining Department · 2023-11-17
- Other Document (FOREST NOC ) · 2024-01-16
- Other Document (UNDERTAKING REGARDING REMAINING NOC ) · 2025-04-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-18
- 2025-Q2 · 2025-12-03
- 2025-Q3 · 2025-12-03
- 2025-Q4 · 2026-01-15
- 2026-Q1 · 2026-05-06
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-15