Overview
LUMINAARA
NVK Real Estate Private Limited · Bandra E-Khar West
Units36
Booked2 of 36As of 2026-10-29
Completion2030-04-30Revised · Proposed 2029-12-31
Registered on2025-10-01
Cases1
Sold0As of 2026-10-29T19:59:33.767Z
Median ₹/sq ft carpet₹45,954As of 2026-10-29T19:59:33.767Z
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 1 case |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details |
| Valuation | 7 ledger details · 1 unit type |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details · 5 professional firms |
| The evidence | |
| Sources | 25 documents · 12 source links |
Registration
Registration
| Promoter | NVK Real Estate Private Limited | |
|---|---|---|
| District | Mumbai Suburban | |
| Locality | Bandra E-Khar West | |
| Regulator | MahaRERA | |
| Registration number | PR1180002501070 | |
| Registered on | 2025-10-01 | |
| Project type | Residential / Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2029-12-31 | |
| Revised completion | 2030-04-30 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum |
|---|---|
| 134 | Bombay High Court |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹26,06,50,000 | |
|---|---|---|
| Construction | ₹18,96,55,724 | |
| Total | ₹55,42,71,296 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 36 | |
|---|---|---|
| Booked | 2 | |
| Booked as of | 2026-10-29 |
Valuation
What is it worth?
Valuation
Unit ledger
| As of | 2026-10-29T19:59:33.767Z | |
|---|---|---|
| Units | 13 | |
| Sold | 0 | |
| Booked | 2 | |
| Unsold | 11 | |
| Median ₹/sq ft carpet | 45,954 | |
| Reckoner ratio, median | 1.188762707918359 |
Ledger by unit type
| Carpet minimum (m²) | Carpet maximum (m²) | Sold | Median ₹/sq ft carpet | Median consideration |
|---|---|---|---|---|
| 60.2 | 101.64 | 0 | 45,954 | ₹3,64,97,500 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2029-12-31 | |
|---|---|---|
| Revised completion | 2030-04-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NVK Real Estate Private Limited | |
|---|---|---|
| Other projects in this city pack | 0 |
Professional firms
| Architect | SKYLINE ARCHITECTS |
| Architect | SpacEra Architects |
| Engineer | STRUCT BOMBAY CONSULTANTS |
| Engineer | SK Consultants & Engineers |
| CA | N B Sayed & Associates |
Sources
Sources
Source URLs & documents
- https://maharera.maharashtra.gov.in/map-projects-search-result
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getFinaceDesignatedBankDetails
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getFinanceEstimatedActualCost
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectGeneralDetailsByProjectId
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectLitigationDetails
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectMeansOfFinance
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectNaPlotWithStructure
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectNaPlotWithoutStructure
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectProfessionalByType
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getProjectSoldUnsoldInventory
- https://maharerait.maharashtra.gov.in/api/maha-rera-public-view-project-registration-service/public/projectregistartion/getUploadedDocuments
- https://maharerait.maharashtra.gov.in/public/project/view/59506
- Declaration Form B · 2025-09-15
- Format B-Opening of RERA Designated Bank Accounts (4).pdf · 2025-09-15
- Luminaara_Form3_Q1_2026-27_19-07-2026_08-19_doc1.pdf · 2026-07-20
- Approved IOD Drawing- Luminaara-1.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-2.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-3.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-4.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-5.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-6.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-7.pdf · 2025-09-18
- Approved IOD Drawing- Luminaara-8.pdf · 2025-09-18
- Others · 2025-09-25
- Format A - All RERA Designated Bank Accounts (6).pdf · 2025-09-25
- Declaration cum Undertaking- Order No-50 -Luminaara.pdf · 2025-09-29
- MCGM_1026894173-16-09-2024 04-00-56$_$DP_RAMDEVI.pdf · 2025-09-30
- MCGM_2482116_IOD_signed.pdf · 2025-09-30
- MCGM_2493688_FirstCC_signed.pdf · 2025-09-30
- MCGM_Provisional_Fire_NOC_Certificate.pdf · 2025-09-30
- MCGM_051701070215248364116.pdf · 2025-09-30
- MCGM_051803070215249430616.pdf · 2025-09-30
- MCGM_052103070215249431016.pdf · 2025-09-30
- MCGM_051501070215249431116.pdf · 2025-09-30
- MCGM_051701070215249634116.pdf · 2025-09-30
- Form 1-Luminaara june 2026.pdf · 2026-07-20
- Luminaara_Form2_Q1_2026-27_20-07-2026_15-08.pdf · 2026-07-20