Overview
NYATI EVARA I
Overview
NYATI EVARA I
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | 1 | – | – | Red flag |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | ||
Title & ownership
We haven't verified this for this project yet.
Sign in first, then it is one click.
Approvals
| Layout approval | 2 filed · latest filed 17 Jul 2017 | |
|---|---|---|
| Building plan approval | 1 filed · latest filed 17 Jul 2017 |
| RERA extensions | None on the filing |
|---|
Disputes & cases
Builder: NYATI BUILDERS PRIVATE LIMITED
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
| Other status 2 | ||||||
|---|---|---|---|---|---|---|
| – | 980 | Civil Judge Senior Division Pune | UNDRI | – | Filed case | –, Medium: The record does not say whether it is decided. |
| – | 519 | Civil Judge Senior Division Pune | UNDRI | – | Filed case | –, Medium: The record does not say whether it is decided. |
20 other registrations under this promoter's exact name in Maharashtra; a complaint on one is listed when MahaRERA lists it.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Projects within 4 km, counted | 21 (21 with an approximate location) | |
|---|---|---|
| Flats in them | 5,518 | |
Location & risks
Construction & progress
Developer
| Estimated cost, at registration | ₹64.72 Cr |
|---|
Loan & collateral
| Building plan | Approval filed with MahaRERA · latest 17 Jul 2017 |
|---|
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 8 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| – |
| – |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
All projects in Pune → (12 of 4,373 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| RERA completion date | 30 Jun 2019 |
|---|
| Registration number | P52100000455 | |
|---|---|---|
| Registered | 18 Jul 2017 |
| Sold or booked |
|---|
| 2,834 of 5,518 (51%) |
| Unsold | 2,684 |
|---|
| Pune Airport | 106.5 |
| Shivajinagar, Pune | 104.5 |
| Pune Junction railway station | 106.5 |
| Hinjawadi | 90 |
| Magarpatta | 112 |
| RERA completion date | 30 Jun 2019 | |
|---|---|---|
| Registered | 18 Jul 2017 |
| Other phases under this promoter name | 18 | |
|---|---|---|
| With a filed extension or completion | 8 (0 completed, 8 extended) | |
| Average schedule slip | 8 months |