Overview
Oceanus Irish Gold
Oceanus Dwellings Pvt Ltd · Kallingal
Units29
Booked9 of 29
Construction progress20%
Completion2030-08-28Proposed
Registered on2025-09-02
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 3 unit types |
| Construction & progress | 3 progress details · 5 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 35 documents · 5 source links |
Registration
Registration
| Promoter | Oceanus Dwellings Pvt Ltd | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | Kallingal | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/TVM/110/2025 | |
| Registered on | 2025-09-02 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2030-08-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/13180/2025 | 2025-04-29 | 2030-04-28 | Thiruvananthapuram Municipal Corporation |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,340 | |
|---|---|---|
| Built-up (m²) | 5,646.52 | |
| Towers | 0 | |
| Units | 29 | |
| Booked | 9 |
Unit types
| Type | Units | Booked | Tower |
|---|---|---|---|
| 3BHK | 10 | 4 | Oceanus Irish Gold |
| 3BHK | 10 | 2 | Oceanus Irish Gold |
| 3BHK | 9 | 3 | Oceanus Irish Gold |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 20% | |
|---|---|---|
| Start | 2025-12-15 | |
| Proposed completion | 2030-08-28 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Oceanus Dwellings Pvt Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 8 |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11937
- https://rera.kerala.gov.in/projects?district=601&page=13
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=Qulh0x17kmb3Y%2FFyvELEOOkQ3ZSXVRSoca5N8MFde9b3Su5YhVH7nF6HcKcgJ4Nf7EYUA4c6w8%2BF8IbfrtsVeupl%2BOCwQxQRCZUz%2BI8Y%2FMy%2F1RIKqk7Xx9nyuDHZ72YIZuGY8VKJJiL6UQnnAm42YaXmnlNGb8Gj4cyQ%2BmwQRGcbkzk7TcpEvA%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11937&Division=1&UserID=30188&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2025-09-02
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-07-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-07-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-07-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-07-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-08-04
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-08-04
- Copy of Valid Building Permit · 2025-07-23
- Detailed technical specifications to be adopted in the project · 2025-07-17 · Sign in to download
- Layout approval plan · 2025-07-16
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2025-07-17 · Sign in to download
- Site Plan / Site Map · 2025-07-16
- Other · 2025-07-17 · Sign in to download
- Other · 2025-07-17 · Sign in to download
- Other · 2025-07-17 · Sign in to download
- Other · 2025-08-02 · Sign in to download
- Clearance from Airport Authority of India · 2025-07-16 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2025-08-04 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2025-08-04 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2025-08-04
- Consent to establish (Clearance from Pollution Control Board) · 2025-07-16 · Sign in to download
- Environment Clearance · 2025-08-04 · Sign in to download
- Initial NOC from Fire and Rescue department · 2025-07-16
- Permission from Water and sewerage department · 2025-08-04 · Sign in to download
- Charts and the project schedule · 2025-07-18 · Sign in to download
- List and details of common amenities · 2025-07-21 · Sign in to download
- Plan of firefighting to be executed in the proposed project · 2025-07-21
- Plan of firefighting to be executed in the proposed project · 2025-07-22
- Plan of firefighting to be executed in the proposed project · 2025-07-22
- Plan of firefighting to be executed in the proposed project · 2025-07-22
- Plan of firefighting to be executed in the proposed project · 2025-07-22
- Plan of firefighting to be executed in the proposed project · 2025-07-22
- Plan of Use of renewable energy to be executed in the proposed project · 2025-07-21