DOSLChhattisgarh Workspace

Overview

OFFICER PARK

OFFICERS PARK · RAIPUR
Units176
Booked105 of 176As of 2024-06-30
Construction progress100%As of 2024-06-30
Completion2024-06-30Revised · Proposed 2023-09-30
Registered on2018-10-16
Approvals3
Cases2

Sections

Property title & search report
Approvals3 approvals
Disputes & cases2 cases
Contract & costs2 cost heads · 23 quarters
Technical report
Site & area3 site details · 176 unit types
Construction & progress4 progress details · 23 quarters
Developer & finance
Developer4 developer details
The evidence
Sources97 documents · 10 source links

Registration

Registration

PromoterOFFICERS PARK
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA161018000817
Registered on2018-10-16
Project typePlotted Development
Status (as filed)Ongoing
Proposed completion2023-09-30
Revised completion2024-06-30