OFFICERS ENCLAVE
SQUARE ONE ASSOCIATES · Patna
Units30
Booked28 of 30As of 2026-09-30
Construction progress100%As of 2026-09-30
Completion2028-02-14Proposed
Registered on2023-04-25
Valid to2028-02-14
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 4 unit types |
| Construction & progress | 4 progress details · 11 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 24 documents · 18 source links |
Registration
Registration
| Promoter | SQUARE ONE ASSOCIATES | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP95723-1/23/R-1561/2023 | |
| Registered on | 2023-04-25 | |
| Valid to | 2028-02-14 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2028-02-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | NAGAR PARISHAD DANAPUR NIZAMAT |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | |
| Notice of Commencement in form X | |
| Fire NOC | DIRECTOR FIRE FIGHTER SERVICE, BIHAR, PATNA |
| Airport NOC | GENERAL MANAGER (ATM)ER,AAI, NSCBI, AIRPORT KOLKATA-700052 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,22,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,882.19 | |
|---|---|---|
| Built-up (m²) | 4,309.4 | |
| FAR | 2.48 | |
| Towers | 1 | |
| Units | 30 | |
| Booked | 28 | |
| Booked as of | 2026-09-30 |
Unit types
| 3 BHK | 12 | OFFICERS ENCLAVE |
| 3 BHK | 12 | OFFICERS ENCLAVE |
| 3 BHK | 3 | OFFICERS ENCLAVE |
| 3 BHK | 3 | OFFICERS ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2023-02-27 | |
| Proposed completion | 2028-02-14 |
Quarterly progress
| 2026-Q3 | 2026-10-05 | 100% | 28 |
| 2026-Q2 | 2026-10-05 | ||
| 2026-Q1 | 2026-10-05 | ||
| 2025-Q4 | 2026-10-05 | ||
| 2025-Q3 | 2026-10-05 | ||
| 2025-Q2 | 2026-10-05 | ||
| 2025-Q1 | 2025-04-25 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SQUARE ONE ASSOCIATES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Canara Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP01282023195723-1
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP01282023195723&ld=pan&pj=RERAP01282023195723-1&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP01282023195723-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-05
- Q1 (Apr - Jun) / 2026-2027 · 2026-10-05
- Q4 (Jan - Mar) / 2025-2026 · 2026-10-05
- Q3 (Oct - Dec) / 2025-2026 · 2026-10-05
- Q2 (Jul - Sep) / 2025-2026 · 2026-10-05
- Q1 (Apr - Jun) / 2025-2026 · 2026-10-05
- Q4-Jan to Mar / 2024-2025 · 2025-04-25
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Other · 2026-10-06 · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q2 · 2026-10-05
- 2026-Q1 · 2026-10-05
- 2025-Q4 · 2026-10-05
- 2025-Q3 · 2026-10-05
- 2025-Q2 · 2026-10-05
- 2025-Q1 · 2025-04-25
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25