Overview
OM ANANT PALACE
Overview
OM ANANT PALACE
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Developer's project loan | No borrowed funds |
|---|
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Jul 2029 |
| Registration number | P51700076615 | |
|---|---|---|
| Registered | 18 Jun 2024 |
Disputes & cases
Builder: YOGESHWAR DEVELOPERS
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Other registrations are grouped only for a company, LLP or firm named in full.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Units filed | 37 | |
|---|---|---|
| Sold | 3 · 8% | |
| Unsold | 34 |
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | No borrowed funds |
|---|
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 28 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
All projects in Thane → · All projects in Mumbai → (12 of 3,110 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| RERA completion date | 31 Jul 2029 | |
|---|---|---|
| Registered | 18 Jun 2024 | |
| Completion date first filed | 31 Mar 2029 |
| Engineer's certificate, Form 2 | 1 filed · latest filed 13 Apr 2026 |
|---|
Land · ₹70.0 L 8.4%Development · ₹7.60 Cr 91.6%
| Estimated cost, at registration | ₹8.30 Cr |
|---|
Sold 8.1%Unsold 91.9%
| Units filed | 37 | |
|---|---|---|
| Sold | 3 · 8% | |
| Unsold | 34 |
| Escrow balance | ₹74,680.51 (INR) | |
|---|---|---|
| Filed withdrawal amount | ₹7,00,319.49 (INR) |