Overview
OMAXE GREENS Phase-II
OMAXE LIMITED · Sahibzada Ajit Singh Nagar (Mohali)
Units210
Completion2020-12-31Proposed
Valid to2020-12-31
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 22 unit types |
| Construction & progress | 2 progress details · 26 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 19 documents · 35 source links |
Registration
Registration
| Promoter | OMAXE LIMITED | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0284 | |
| Valid to | 2020-12-31 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2020-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Clearances (Received) | 2017-05-05 |
| License as Promoter from competent Authority | 2017-12-04 | |
| License from Competent Authority | ||
| Other Document (Letter of Regulatory Clearances LORC I) | Clearances (Received) | 2017-05-16 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹80,77,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 22,740 | |
|---|---|---|
| Towers | 20 | |
| Maximum floors | 5 | |
| Units | 210 |
Unit types
| 3 BHK | 100.8 | 8 | TOWER -3 |
| 3 BHK | 100.8 | 8 | TOWER -4 |
| 3 BHK | 100.8 | 10 | TOWER-14 |
| 3 BHK | 100.8 | 10 | TOWER-15 |
| 3 BHK | 100.8 | 10 | TOWER-16 |
| 3 BHK | 100.8 | 10 | TOWER-17 |
| 3 BHK | 100.8 | 10 | TOWER-18 |
| 3 BHK | 100.8 | 10 | TOWER-19 |
| 3 BHK | 100.8 | 10 | TOWER-20 |
| 2 BHK (Type-A) | 78.22 | 10 | TOWER-11 |
| 2 BHK (Type-B) | 76.92 | 10 | TOWER-11 |
| 2 BHK (Type-A) | 78.22 | 10 | TOWER-12 |
| 2 BHK (Type-B) | 76.92 | 10 | TOWER-12 |
| 3 BHK | 100.8 | 10 | TOWER-12A |
| 3 BHK | 100.8 | 8 | TOWER -1 |
| 3 BHK | 100.8 | 8 | TOWER -2 |
| 3 BHK | 100.8 | 8 | TOWER -5 |
| 3 BHK | 100.8 | 10 | TOWER -6 |
| 3 BHK | 100.8 | 10 | TOWER -7 |
| 3 BHK | 100.8 | 10 | TOWER -8 |
| 3 BHK | 100.8 | 10 | TOWER -9 |
| 3 BHK | 100.8 | 10 | TOWER-10 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-02-09 | |
|---|---|---|
| Proposed completion | 2020-12-31 |
Quarterly progress
| 2020-Q2 | 2020-08-31 |
| 2020-Q3 | 2020-11-25 |
| 2021-Q1 | 2021-05-10 |
| 2020-Q4 | 2021-06-23 |
| 2021-Q2 | 2021-07-22 |
| 2021-Q3 | 2021-10-30 |
| 2021-Q4 | 2022-02-01 |
| 2022-Q1 | 2022-04-25 |
| 2022-Q2 | 2022-07-27 |
| 2022-Q3 | 2022-11-01 |
| 2022-Q4 | 2023-01-17 |
| 2023-Q1 | 2023-05-01 |
| 2023-Q2 | 2023-07-17 |
| 2023-Q3 | 2023-10-16 |
| 2023-Q4 | 2024-01-17 |
| 2024-Q1 | 2024-04-16 |
| 2024-Q2 | 2024-07-11 |
| 2024-Q3 | 2024-10-15 |
| 2024-Q4 | 2025-01-09 |
| 2025-Q1 | 2025-04-09 |
| 2025-Q2 | 2025-07-11 |
| 2025-Q3 | 2025-10-09 |
| 2025-Q4 | 2026-01-08 |
| 2026-Q1 | 2026-04-08 |
| 2026-Q2 | 2026-07-09 |
| 2026-Q3 | 2026-10-14 |
Extensions
| Valid to |
|---|
| 2025-12-02 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | OMAXE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Axis Bank Limited | |
| Other projects in this city pack | 18 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10047&inPromoter_ID=1057&inPromoterType=2
- Approved Layout Plan
- Approved Project Site Map · Sign in to download
- Approved Sanctioned Plan
- Approved Sanctioned Plan
- Approved Sanctioned Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2017-05-05
- License as Promoter from competent Authority · 2017-12-04
- License from Competent Authority
- Other Document (Letter of Regulatory Clearances LORC I) · 2017-05-16
- Other Document (LORC 2) · 2017-04-21 · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- CLU Certificate
- Environment Clearance certificate/ NOC · 2017-05-05
- License as Promoter from competent Authority · 2017-12-04
- License from Competent Authority
- Other Document (Letter of Regulatory Clearances LORC I) · 2017-05-16
- Extension order · Sign in to download
- 2020-Q2 · 2020-08-31
- 2020-Q3 · 2020-11-25
- 2021-Q1 · 2021-05-10
- 2020-Q4 · 2021-06-23
- 2021-Q2 · 2021-07-22
- 2021-Q3 · 2021-10-30
- 2021-Q4 · 2022-02-01
- 2022-Q1 · 2022-04-25
- 2022-Q2 · 2022-07-27
- 2022-Q3 · 2022-11-01
- 2022-Q4 · 2023-01-17
- 2023-Q1 · 2023-05-01
- 2023-Q2 · 2023-07-17
- 2023-Q3 · 2023-10-16
- 2023-Q4 · 2024-01-17
- 2024-Q1 · 2024-04-16
- 2024-Q2 · 2024-07-11
- 2024-Q3 · 2024-10-15
- 2024-Q4 · 2025-01-09
- 2025-Q1 · 2025-04-09
- 2025-Q2 · 2025-07-11
- 2025-Q3 · 2025-10-09
- 2025-Q4 · 2026-01-08
- 2026-Q1 · 2026-04-08
- 2026-Q2 · 2026-07-09
- 2026-Q3 · 2026-10-14