Overview
OMKAR DAFFODILS
KAMDHENU REALTY PVT LTD · Lucknow
Units264
Completion2021-09-02Revised · Proposed 2021-03-03
Registered on2017-10-31
Valid to2021-09-02
Approvals1
Complaints2As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 2 project complaints · 3 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 98 unit types |
| Construction & progress | 3 progress details · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 1 document · 7 source links |
Registration
Registration
| Promoter | KAMDHENU REALTY PVT LTD | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ14196 | |
| Registered on | 2017-10-31 | |
| Valid to | 2021-09-02 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2021-03-03 | |
| Revised completion | 2021-09-02 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 1536 | 2016-06-03 | 2021-06-02 | U.P. Awas Evam Vikas Parishad |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 2 | |
|---|---|---|
| Promoter | 3 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹6,00,00,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 17,779 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 12 | |
| Units | 264 |
Unit types
| OTHER | 5,866.03 | 0 | Omkar Daffdils | BSMNT |
| OTHER | 1,150 | 0 | Omkar Daffdils | GF |
| 4 BHK | 133 | 1 | Omkar Daffdils | 1 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 1 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 1 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 1 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 1 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 1 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 1 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 1 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 2 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 2 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 2 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 2 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 2 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 2 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 2 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 2 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 3 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 3 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 3 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 3 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 3 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 3 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 3 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 3 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 4 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 4 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 4 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 4 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 4 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 4 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 4 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 4 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 5 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 5 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 5 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 5 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 5 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 5 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 5 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 5 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 6 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 6 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 6 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 6 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 6 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 6 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 6 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 6 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 7 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 7 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 7 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 7 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 7 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 7 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 7 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 7 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 8 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 8 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 8 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 8 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 8 |
| 2 BHK | 8.87 | 1 | Omkar Daffdils | 8 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 8 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 8 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 9 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 9 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 9 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 9 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 9 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 9 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 9 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 9 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 10 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 10 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 10 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 10 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 10 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 10 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 10 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 10 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 11 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 11 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 11 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 11 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 11 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 11 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 11 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 11 |
| 4 BHK | 133 | 1 | Omkar Daffdils | 12 |
| 4 BHK | 124.03 | 1 | Omkar Daffdils | 12 |
| 3 BHK | 103.09 | 1 | Omkar Daffdils | 12 |
| 3 BHK | 96.37 | 1 | Omkar Daffdils | 12 |
| 2 BHK | 79.3 | 4 | Omkar Daffdils | 12 |
| 2 BHK | 80.87 | 1 | Omkar Daffdils | 12 |
| 2 BHK | 69.55 | 8 | Omkar Daffdils | 12 |
| 2 BHK | 76.45 | 5 | Omkar Daffdils | 12 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-11-15 | |
|---|---|---|
| Proposed completion | 2021-03-03 | |
| Revised completion | 2021-09-02 |
Extensions
| Valid to | Reason |
|---|---|
| 2021-09-02 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KAMDHENU REALTY PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Contractor | G.N. Group & Company |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=GuE/K8t4ud0=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=n7gfd/8V3zWcFEHfrrqvzA==&PaURJEMAN4=ZL9MNERkNdbAccrodF3bdQ==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=GuE/K8t4ud0=
- Sanctioned Building/ Block Plan (Add Plans for All Buildings or Blocks) · 2017-10-31