Overview
One City Hamlet-4 (Formerly known as HAMLET-4)
PUMA REALTORS PRIVATE LIMITED · Sahibzada Ajit Singh Nagar (Mohali)
Units264
Completion2022-12-31Proposed
Valid to2022-12-31
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 49 unit types |
| Construction & progress | 2 progress details · 35 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 47 source links |
Registration
Registration
| Promoter | PUMA REALTORS PRIVATE LIMITED | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0330 | |
| Valid to | 2022-12-31 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2011-04-06 |
| Application for renewal of any of the NOCs/ Licenses | 2017-09-25 | |
| Electric Substation NOC | 2023-02-27 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2024-11-04 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2012-11-30 |
| License as Promoter from competent Authority | 2025-04-28 | |
| Other Document (Forest NOC) | 2022-06-22 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-02-26 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹100 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 68,475.55 | |
|---|---|---|
| Units | 264 |
Unit types
| B3 | 215.46 | 20 | HAMLET-4 |
| B1 | 189 | 24 | HAMLET-4 |
| B8 | 134.46 | 5 | HAMLET-4 |
| B7 | 171.77 | 3 | HAMLET-4 |
| B4 | 126.24 | 4 | HAMLET-4 |
| B4-1 | 132.02 | 2 | HAMLET-4 |
| B4-2 | 126.94 | 1 | HAMLET-4 |
| B2 | 215.67 | 9 | HAMLET-4 |
| B2-A | 215.67 | 1 | HAMLET-4 |
| B5 | 102.09 | 4 | HAMLET-4 |
| B6 | 121.28 | 3 | HAMLET-4 |
| C7-A | 141.82 | 1 | HAMLET-4 |
| C7 | 148.95 | 2 | HAMLET-4 |
| C7 | 148.95 | 1 | HAMLET-4 |
| C | 148.95 | 2 | HAMLET-4 |
| C | 148.95 | 1 | HAMLET-4 |
| C7-B | 130.08 | 1 | HAMLET-4 |
| C7-C | 99.14 | 1 | HAMLET-4 |
| C5 | 128 | 2 | HAMLET-4 |
| C5 | 128 | 1 | HAMLET-4 |
| C5 | 128 | 9 | HAMLET-4 |
| C5 | 128 | 2 | HAMLET-4 |
| C5 | 128 | 10 | HAMLET-4 |
| C5 | 128 | 5 | HAMLET-4 |
| C5 | 128 | 2 | HAMLET-4 |
| C5 | 128 | 11 | HAMLET-4 |
| C5-F | 160 | 1 | HAMLET-4 |
| C5-A | 132.16 | 1 | HAMLET-4 |
| C6 | 114.8 | 4 | HAMLET-4 |
| C5-F | 160 | 1 | HAMLET-4 |
| C5-A | 132.16 | 1 | HAMLET-4 |
| C5 | 128 | 11 | HAMLET-4 |
| C5-D | 165.44 | 1 | HAMLET-4 |
| C5 | 128 | 1 | HAMLET-4 |
| C5 | 128 | 10 | HAMLET-4 |
| C5 | 128 | 1 | HAMLET-4 |
| C5-D | 165.44 | 1 | HAMLET-4 |
| C5 | 128 | 12 | HAMLET-4 |
| C5-B | 145.92 | 1 | HAMLET-4 |
| C5-E | 126.4 | 15 | HAMLET-4 |
| C5 | 128 | 5 | HAMLET-4 |
| C5 | 128 | 21 | HAMLET-4 |
| C2 | 129.6 | 3 | HAMLET-4 |
| C7 | 129.56 | 7 | HAMLET-4 |
| B9 | 167.445 | 9 | HAMLET-4 |
| C5 | 128 | 7 | HAMLET-4 |
| B9-A | 149.15 | 2 | HAMLET-4 |
| B9 | 167.45 | 16 | HAMLET-4 |
| B10 | 184.61 | 6 | HAMLET-4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-03-27 | |
|---|---|---|
| Proposed completion | 2022-12-31 |
Quarterly progress
| 2018-Q1 | 2021-11-19 |
| 2018-Q2 | 2021-11-19 |
| 2018-Q3 | 2021-11-19 |
| 2018-Q4 | 2021-11-19 |
| 2019-Q1 | 2021-11-19 |
| 2019-Q2 | 2021-11-19 |
| 2019-Q3 | 2021-11-22 |
| 2019-Q4 | 2021-11-22 |
| 2020-Q1 | 2021-11-22 |
| 2020-Q2 | 2021-11-22 |
| 2020-Q3 | 2021-11-22 |
| 2020-Q4 | 2021-11-22 |
| 2021-Q1 | 2021-11-22 |
| 2021-Q2 | 2021-11-22 |
| 2021-Q3 | 2021-11-22 |
| 2021-Q4 | 2022-04-12 |
| 2022-Q1 | 2022-04-12 |
| 2022-Q2 | 2022-07-15 |
| 2022-Q3 | 2022-10-15 |
| 2022-Q4 | 2023-01-14 |
| 2023-Q1 | 2023-04-15 |
| 2023-Q2 | 2023-07-15 |
| 2023-Q3 | 2023-10-14 |
| 2023-Q4 | 2024-01-15 |
| 2024-Q1 | 2024-04-14 |
| 2024-Q2 | 2024-07-15 |
| 2024-Q3 | 2024-10-14 |
| 2024-Q4 | 2025-01-15 |
| 2025-Q1 | 2025-04-15 |
| 2025-Q2 | 2025-07-14 |
| 2025-Q3 | 2025-10-15 |
| 2025-Q4 | 2026-03-18 |
| 2026-Q1 | 2026-04-14 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-15 |
Extensions
| Valid to |
|---|
| 2025-12-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PUMA REALTORS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Kotak Mahindra Bank Limited | |
| Other projects in this city pack | 9 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10041&inPromoter_ID=1056&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site Map · Sign in to download
- Approved Sanctioned Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2011-04-06
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2018-03-27
- Application for renewal of any of the NOCs/ Licenses · 2017-09-25
- Borewell Registration certificate from Central Ground Water Authority · 2011-08-19
- Commencement Certificate (Mega Project Category) · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Completion/ Phase Completion certificate from Municipal/ Competent Authority · 2017-06-30 · Sign in to download
- Electric Substation NOC · 2023-02-27
- Environment Clearance certificate/ NOC · 2024-11-04
- Environment Clearance certificate/ NOC · 2012-11-30
- License as Promoter from competent Authority · 2025-04-28
- Other Document (Forest NOC) · 2022-06-22
- Pollution Clearance from Punjab Pollution Control Board · 2024-02-26
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2011-04-06
- Application for renewal of any of the NOCs/ Licenses · 2017-09-25
- Electric Substation NOC · 2023-02-27
- Environment Clearance certificate/ NOC · 2024-11-04
- Environment Clearance certificate/ NOC · 2012-11-30
- License as Promoter from competent Authority · 2025-04-28
- Other Document (Forest NOC) · 2022-06-22
- Pollution Clearance from Punjab Pollution Control Board · 2024-02-26
- Extension order · Sign in to download
- 2018-Q1 · 2021-11-19
- 2018-Q2 · 2021-11-19
- 2018-Q3 · 2021-11-19
- 2018-Q4 · 2021-11-19
- 2019-Q1 · 2021-11-19
- 2019-Q2 · 2021-11-19
- 2019-Q3 · 2021-11-22
- 2019-Q4 · 2021-11-22
- 2020-Q1 · 2021-11-22
- 2020-Q2 · 2021-11-22
- 2020-Q3 · 2021-11-22
- 2020-Q4 · 2021-11-22
- 2021-Q1 · 2021-11-22
- 2021-Q2 · 2021-11-22
- 2021-Q3 · 2021-11-22
- 2021-Q4 · 2022-04-12
- 2022-Q1 · 2022-04-12
- 2022-Q2 · 2022-07-15
- 2022-Q3 · 2022-10-15
- 2022-Q4 · 2023-01-14
- 2023-Q1 · 2023-04-15
- 2023-Q2 · 2023-07-15
- 2023-Q3 · 2023-10-14
- 2023-Q4 · 2024-01-15
- 2024-Q1 · 2024-04-14
- 2024-Q2 · 2024-07-15
- 2024-Q3 · 2024-10-14
- 2024-Q4 · 2025-01-15
- 2025-Q1 · 2025-04-15
- 2025-Q2 · 2025-07-14
- 2025-Q3 · 2025-10-15
- 2025-Q4 · 2026-03-18
- 2026-Q1 · 2026-04-14
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-15