Overview
Opus
JINDALSONS INFRATEX PVT. LTD. · Ghaziabad
Units152
Completion2027-04-12Proposed
Registered on2022-06-15
Valid to2027-04-12
Approvals1
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 39 unit types |
| Construction & progress | 2 progress details · 16 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 56 documents · 23 source links |
Registration
Registration
| Promoter | JINDALSONS INFRATEX PVT. LTD. | |
|---|---|---|
| District | Ghaziabad | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ249398 | |
| Registered on | 2022-06-15 | |
| Valid to | 2027-04-12 | |
| Project type | Commercial | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2027-04-12 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | Retail Shop/03667/UPAVP/BP/21-22/1644/24032022 | 2022-04-13 | 2027-04-12 | U.P. Awas Evam Vikas Parishad |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹51,82,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,019 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 3 | |
| Units | 152 |
Unit types
| SHOP | 24.66 | 2 | Opus | BSMNT |
| SHOP | 5.13 | 2 | Opus | BSMNT |
| SHOP | 15.5 | 4 | Opus | BSMNT |
| SHOP | 15.96 | 2 | Opus | BSMNT |
| SHOP | 16.77 | 2 | Opus | BSMNT |
| SHOP | 18.29 | 4 | Opus | BSMNT |
| SHOP | 16.95 | 4 | Opus | BSMNT |
| SHOP | 18.53 | 2 | Opus | BSMNT |
| SHOP | 20.22 | 4 | Opus | BSMNT |
| SHOP | 18.45 | 8 | Opus | BSMNT |
| SHOP | 24.66 | 2 | Opus | GF |
| SHOP | 16.77 | 6 | Opus | GF |
| SHOP | 16.63 | 6 | Opus | GF |
| SHOP | 16.95 | 12 | Opus | GF |
| SHOP | 5.13 | 2 | Opus | GF |
| SHOP | 15.5 | 4 | Opus | GF |
| SHOP | 15.96 | 2 | Opus | GF |
| SHOP | 10.15 | 2 | Opus | 1 |
| SHOP | 13.68 | 2 | Opus | 1 |
| SHOP | 5.13 | 2 | Opus | 1 |
| SHOP | 15.5 | 4 | Opus | 1 |
| SHOP | 15.96 | 2 | Opus | 1 |
| SHOP | 16.77 | 6 | Opus | 1 |
| SHOP | 16.63 | 6 | Opus | 1 |
| SHOP | 16.95 | 12 | Opus | 1 |
| SHOP | 10.15 | 2 | Opus | 2 |
| SHOP | 13.68 | 2 | Opus | 2 |
| SHOP | 5.13 | 2 | Opus | 2 |
| SHOP | 15.5 | 4 | Opus | 2 |
| SHOP | 15.96 | 2 | Opus | 2 |
| SHOP | 16.77 | 6 | Opus | 2 |
| SHOP | 16.63 | 6 | Opus | 2 |
| SHOP | 16.95 | 12 | Opus | 2 |
| SHOP | 9.86 | 4 | Opus | 3 |
| SHOP | 10.17 | 2 | Opus | 3 |
| SHOP | 31.86 | 2 | Opus | 3 |
| SHOP | 43.05 | 1 | Opus | 3 |
| SHOP | 18.6 | 2 | Opus | 3 |
| SHOP | 21.06 | 1 | Opus | 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-04-13 | |
|---|---|---|
| Proposed completion | 2027-04-12 |
Quarterly progress
| 2022-Q2 | |
| 2022-Q3 | |
| 2022-Q4 | |
| 2023-Q1 | |
| 2023-Q2 | |
| 2023-Q3 | |
| 2023-Q4 | |
| 2024-Q1 | |
| 2024-Q2 | |
| 2024-Q3 | |
| 2024-Q4 | |
| 2025-Q1 | |
| 2025-Q2 | |
| 2025-Q3 | 98.46% |
| 2025-Q4 | 99.04% |
| 2026-Q1 | 98% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | JINDALSONS INFRATEX PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=fk7EWO2jAxU=&hfFlag=q5Tk0QUeJB8oatkp/Oqbxw==&NPJ6RAme=w/Ahd5YyCYk=&PaURJEMAN4=ZL9MNERkNdYAUDlEc9xXhQ==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GHAZIABAD
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=fk7EWO2jAxU=
- Commencement Certificate · 2022-04-28
- Waste Disposal Plan · 2022-04-28
- Water Supply Plan · 2022-05-21
- Electricity Supply Plan · 2022-04-28
- Development Work Plan · 2022-04-28
- CA CERTIFICATE · 2022-04-28 · Sign in to download
- ARCHITECT CERTIFICATE · 2022-04-28 · Sign in to download
- ENGINEERS CERTIFICATE · 2022-04-28 · Sign in to download
- Other · 2022-04-28 · Sign in to download
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- 2022-Q2
- 2022-Q3
- 2022-Q4
- 2023-Q1
- 2023-Q2
- 2023-Q3
- 2023-Q4
- 2024-Q1
- 2024-Q2
- 2024-Q3
- 2024-Q4
- 2025-Q1
- 2025-Q2
- 2025-Q3
- 2025-Q4
- 2026-Q1